Construction unit costs in Wyoming

Median awarded unit prices for the 42 most-bid items on Wyoming public projects, from winning bids in agency bid tabulations.

Cost by state › Wyoming

ItemPerMedianMiddle halfWinning bids
Flagginghour$48.98$39.25 – $54.11196
Crushed Basecubic yard$96.84$64.65 – $130.00113
Motor Graderhour$210.00$193.50 – $230.00110
Tack Coatton$895.00$796.25 – $1,08890
Sign Panels, Aluminumsquare foot$62.83$53.00 – $75.6288
Hydrated Limeton$268.00$231.25 – $318.1586
Unclassified Excavationcubic yard$26.50$13.40 – $42.0083
Seeding (Pls)pound$44.50$30.49 – $66.0082
Topsoil Storingcubic yard$4.45$3.00 – $8.3579
Fertilizer Type Ipound$8.32$7.00 – $10.4478
Flexible Delineators, Type Iieach$85.25$80.00 – $92.5077
Topsoil Placingcubic yard$5.00$3.15 – $10.0076
Dry Mulchton$470.00$338.50 – $585.3375
Portable Variable Message Signeach$7,000$3,754 – $9,73671
Flexible Delineators, Type Iiieach$85.62$79.00 – $92.5070
Removal of Fencelinear foot$1.48$0.853 – $2.2466
End Panelseach$397.50$339.75 – $450.0064
Reference Markerseach$121.00$107.50 – $151.4863
Reference Marker Panelseach$137.00$103.50 – $168.7563
Hot Plant Mixton$90.55$67.52 – $145.9062
Cutting Bit Pvmtlinear foot$4.60$2.50 – $8.7061
Test Stripeach$17,500$14,879 – $24,10059
Thermoplastic Pavement Markingssquare foot$40.00$32.50 – $49.6755
Brace Panelseach$300.00$269.75 – $350.0054
SIGN POSTS, WOOD 4 X 6 inlinear foot$37.00$32.00 – $41.0053
SIGN POSTS, WOOD 6 X 6 inlinear foot$39.00$31.00 – $48.0053
Fog Sealton$1,271$917.38 – $1,50552
Emulsified Asphalt Modifiedton$837.88$770.42 – $941.6748
Removal of Guardraillinear foot$4.25$3.00 – $6.2946
SIGN POSTS, WOOD 6 X 8 inlinear foot$40.98$33.62 – $54.7546
Crack Seal (Plant Mix)linear foot$0.92$0.823 – $1.0146
Machine-Placed Riprapcubic yard$245.00$205.00 – $319.8543
Curb and Gutter Type Alinear foot$70.00$54.62 – $91.1242
Removal Of Surfacingsquare yard$15.00$7.75 – $31.2039
Geotextile (Erosion Control)square yard$5.75$3.83 – $10.9739
Reclaimed Asphalt Pavement Wideningcubic yard$10.00$5.04 – $14.2536
Hot Plant Mix (Recycle)ton$70.87$60.90 – $82.4336
Temporary Concrete Barrierlinear foot$34.80$23.75 – $54.0035
Class A Concretecubic yard$2,230$1,800 – $3,52025
Erosion Control Blanketsquare yard$3.50$3.08 – $4.4024
Flowable Backfillcubic yard$675.00$334.25 – $1,02618
MGS Guardraillinear foot$63.00$32.25 – $77.0015