| Class 1 Excavation | cubic yard | $44.00 | $29.88 – $70.00 | 895 |
| Type 31-S Guide Rail | linear foot | $27.50 | $21.25 – $38.00 | 827 |
| Additional Traffic Control Signs | square foot | $7.90 | $6.50 – $11.50 | 813 |
| Remove Existing Guide Rail (Contractor'S Property) | linear foot | $2.60 | $2.00 – $5.00 | 775 |
| Geotextile, Class 4, Type A | square yard | $3.50 | $3.00 – $4.50 | 743 |
| Reinforcement Bars (Epoxy Coated) | pound | $2.58 | $2.00 – $3.96 | 704 |
| Permanent Impact Attenuating Device, Type Ii, Test Level 3, Tangent (Mash) | each | $3,000 | $2,653 – $3,360 | 682 |
| Compost Filter Sock 12 Inch Diameter | linear foot | $7.00 | $5.00 – $10.00 | 615 |
| Asphalt Tack Coat (Ntt/Cntt) | square yard | $0.46 | $0.3 – $1.00 | 612 |
| Saw Cutting | linear foot | $5.75 | $4.00 – $10.00 | 538 |
| Seeding And Soil Supplements - Formula B Residential Mix, Including Mulch | pound | $52.00 | $30.00 – $120.00 | 537 |
| Post Mounted Signs, Type F | square foot | $29.00 | $22.65 – $43.52 | 528 |
| Pumped Water Filter Bag | each | $1,240 | $747.50 – $1,826 | 515 |
| Topsoil Furnished and Placed | cubic yard | $92.00 | $71.00 – $130.00 | 505 |
| Subbase 6" Depth (No. 2A) | square yard | $20.00 | $15.00 – $27.10 | 493 |
| 4" Standard Pavement Markings, Paint & Beads, Yellow | linear foot | $0.32 | $0.2 – $0.7 | 490 |
| Post Mounted Signs, Type B | square foot | $58.45 | $46.00 – $77.00 | 480 |
| Additional Warning Lights, Type B | day | $1.05 | $1.00 – $1.30 | 480 |
| Replacement Pumped Water Filter Bag | each | $619.64 | $308.50 – $922.50 | 475 |
| 4" Standard Pavement Markings, Paint & Beads, White | linear foot | $0.34 | $0.2 – $0.75 | 473 |
| Type 31-Strong Post In-Line Anchor | each | $1,100 | $1,000 – $1,444 | 456 |
| Temporary Protective Fence | linear foot | $5.00 | $4.00 – $8.00 | 404 |
| Remove Post Mounted Signs, Type B | each | $58.27 | $44.02 – $87.05 | 402 |
| Guide Rail Mounted Delineator Type B, (W/W) | each | $18.39 | $16.00 – $22.00 | 394 |
| Inlet Filter Bag For Type M Inlet | each | $250.00 | $175.00 – $333.02 | 388 |
| Class 2 Excavation | cubic yard | $60.00 | $38.30 – $96.25 | 383 |
| Pavement Marking Removal | square foot | $4.83 | $2.48 – $7.00 | 380 |
| Reset Post Mounted Signs, Type B | each | $215.78 | $180.00 – $295.95 | 376 |
| Flexible Delineator Post, Ground-Mount Type Gm-2, Red Post With White/Blank Sheeting | each | $55.77 | $45.00 – $68.00 | 376 |
| Standard Inlet Box, Height < /= 10' | each | $3,972 | $3,300 – $4,500 | 374 |
| Temporary Short-Term, Rolled Erosion Control Product, Type 2D | square yard | $2.10 | $1.90 – $3.00 | 373 |
| Geotextile, Class 1 | linear foot | $3.26 | $2.24 – $4.68 | 355 |
| Rock Construction Entrance | each | $3,500 | $2,671 – $5,000 | 346 |
| Milling Of Asphalt Pavement Surface, Variable Depth, Milled Material Retained By Contractor | square yard | $7.99 | $4.00 – $17.87 | 335 |
| 24" White Hot Thermoplastic Pavement Markings | linear foot | $15.00 | $10.00 – $21.01 | 332 |
| 6" Pavement Base Drain | linear foot | $21.90 | $18.13 – $29.00 | 327 |
| Subbase (No. 2A) | ton | $62.00 | $48.00 – $85.00 | 327 |
| 6" Subsurface Drain Outlets | linear foot | $27.72 | $21.00 – $38.92 | 325 |
| 66" Red Subsurface Drain Outlet Marker | each | $60.31 | $48.00 – $73.00 | 317 |
| Guide Rail Mounted Delineator Type B, (W/B) | each | $18.50 | $16.00 – $22.53 | 312 |
| Asphalt Tack Coat | square yard | $0.75 | $0.3 – $1.50 | 309 |
| Type 31-Sc Guide Rail | linear foot | $32.00 | $30.00 – $37.85 | 304 |
| Buried-In-Backslope Terminal, Single Panel | each | $1,061 | $842.55 – $1,319 | 292 |
| Class 3 Excavation | cubic yard | $60.26 | $35.00 – $87.00 | 164 |
| Arrow Panel | each | $2,500 | $1,000 – $4,805 | 155 |
| Pavement Marking Removal | linear foot | $1.12 | $0.762 – $1.50 | 30 |
| Temporary Concrete Barrier | linear foot | $40.15 | $30.09 – $52.25 | 18 |