Aggregate base course class 5: cost per ton in Burleigh County, ND

Listed by the agency as “Aggregate Base Course CL 5”.

The median awarded price is $53.90 per ton, from 21 winning bids on 21 public projects in Burleigh County, ND (2022–2026). Half of the awarded prices fall between $42.00 and $74.70.

Cost by state › North Dakota › Burleigh County › Aggregate Base Course CL 5

$53.90median per ton
$42.00 – $74.70middle half (25th–75th percentile)
21winning bids, 21 source documents
2022–2026lettings covered (last 5 years)

Winning bids only, as printed in the agencies' bid tabulations (Burleigh County, NDDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $65.00 in 2023 to $42.00 in 2025 (-35%).

YearMedian per tonWinning bids
2023$65.008
2025$42.005

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Jun 12, 2026NDDOT9480 TON$40.00project IM-BGR-1-094(253)176 ↗
Apr 28, 2026Burleigh County125 TON$43.66Open bid tab, 0193 ↗
Mar 27, 2026NDDOT824 TON$60.00project BRC-0815(054) ↗
Dec 12, 2025NDDOT1173.2 TON$74.70project IM-1-094(236)157 ↗
Nov 14, 2025NDDOT97 TON$105.00project HEU-1-981(133) ↗