Other · awarded bid prices
Pipe, Remove: cost per linear foot in Indiana
The median awarded price is $38.00 per linear foot, from 298 winning bids on 291 public projects in Indiana (2023–2026). Half of the awarded prices fall between $20.62 and $61.70.
Cost by state › Indiana › Pipe, Remove
$38.00median per linear foot
$20.62 – $61.70middle half (25th–75th percentile)
298winning bids, 291 source documents
2023–2026lettings covered (last 3 years)
Winning bids only, as printed in the agencies' bid tabulations (INDOT). These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $30.12 in 2021 to $40.00 in 2026 (+33%).
| Year | Median per linear foot | Winning bids |
|---|---|---|
| 2021 | $30.12 | 76 |
| 2022 | $34.50 | 84 |
| 2023 | $39.70 | 104 |
| 2024 | $40.00 | 111 |
| 2025 | $35.37 | 94 |
| 2026 | $40.00 | 76 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Sep 2, 2026 | INDOT | 173 LFT | $35.00 | Sep 2, 2026 letting ↗ |
| Sep 2, 2026 | INDOT | 120 LFT | $1.00 | Sep 2, 2026 letting ↗ |
| Sep 2, 2026 | INDOT | 241 LFT | $50.00 | Sep 2, 2026 letting ↗ |
| Sep 2, 2026 | INDOT | 135 LFT | $27.00 | Sep 2, 2026 letting ↗ |
| Aug 5, 2026 | INDOT | 20 LFT | $196.00 | Aug 5, 2026 letting ↗ |
See every awarded price for this item, in all states, on the Pipe, Remove item page.
Related items in Indiana
- Computer System Equipment: $750.00 per each
- Reinforcing Bars, Epoxy Coated: $1.75 per pound
- Pump Around: $10,000 per each
- Line, Remove: $0.71 per linear foot
- Line, Multi-component, Solid, White, 6 IN.: $1.14 per linear foot
- Right of Way Marker: $195.00 per each
- Threaded Tie Bar Assembly, Epoxy Coated: $50.00 per each
- Law Enforcement Officer: $60.00 per hour