Pavement Message Marking, Thermoplastic Lane Indication Arrow: cost per each in Lake County, IN
The median awarded price is $219.00 per each, from 12 winning bids on 12 public projects in Lake County, IN (2024–2026). Half of the awarded prices fall between $194.75 and $225.75.
Cost by state › Indiana › Lake County › Pavement Message Marking, Thermoplastic Lane Indication Arrow
Winning bids only, as printed in the agencies' bid tabulations (INDOT). The county is the one the agency recorded for the project. These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.
Trend
The median awarded price went from $100.00 in 2020 to $219.00 in 2025 (+119%).
| Year | Median per each | Winning bids |
|---|---|---|
| 2020 | $100.00 | 7 |
| 2023 | $135.00 | 5 |
| 2025 | $219.00 | 7 |
Most recent source documents
| Letting | Agency | Quantity | Awarded unit price | Source |
|---|---|---|---|---|
| Jul 8, 2026 | INDOT | 32 EACH | $125.00 | Jul 8, 2026 letting ↗ |
| May 7, 2026 | INDOT | 20 EACH | $185.00 | May 7, 2026 letting ↗ |
| Dec 10, 2025 | INDOT | 4 EACH | $219.00 | Dec 10, 2025 letting ↗ |
| Jul 9, 2025 | INDOT | 53 EACH | $233.00 | Jul 9, 2025 letting ↗ |
| May 7, 2025 | INDOT | 9 EACH | $219.00 | May 7, 2025 letting ↗ |
See every awarded price for this item on the Pavement Message Marking, Thermoplastic Lane Indication Arrow item page.
Related items in Lake County
- Construction Sign, Type A: $220.50 per each
- Construction Sign, Type B: $116.00 per each
- Grooving FOR Pavement Markings: $0.695 per linear foot
- Road Closure Sign Assembly: $288.50 per each
- Construction Sign, a: $196.50 per each
- Flashing Arrow Sign: $15.00 per day
- Barricade, Type Iii-a: $15.52 per linear foot
- Barricade, Type Iii-b: $15.39 per linear foot