Paving · awarded bid prices

Processed Aggregate Base: cost per cubic yard in Connecticut

The median awarded price is $80.00 per cubic yard, from 91 winning bids on 91 public projects in Connecticut (2023–2026). Half of the awarded prices fall between $60.50 and $123.50.

Cost by state › Connecticut › Processed Aggregate Base

$80.00median per cubic yard
$60.50 – $123.50middle half (25th–75th percentile)
91winning bids, 91 source documents
2023–2026lettings covered (last 3 years)

Winning bids only, as printed in the agencies' bid tabulations (CTDOT). These are prices agencies awarded, not quotes: a price on a given job depends on quantity, location and timing, and the figures here are not adjusted for any of them.

Trend

The median awarded price went from $54.25 in 2021 to $75.00 in 2026 (+38%).

YearMedian per cubic yardWinning bids
2021$54.2522
2022$60.0027
2023$66.2025
2024$85.0033
2025$82.0037
2026$75.0017

Most recent source documents

LettingAgencyQuantityAwarded unit priceSource
Oct 28, 2026CTDOT250 c.y.$75.00line 0260 ↗
Aug 12, 2026CTDOT115 c.y.$100.00line 0150 ↗
Aug 12, 2026CTDOT957 c.y.$74.00line 0180 ↗
Aug 5, 2026CTDOT2085 c.y.$80.00line 0200 ↗
Jul 29, 2026CTDOT5134 c.y.$52.50line 0380 ↗

See every awarded price for this item, in all states, on the Processed Aggregate Base item page.