| Public information service | ls | 244 | $2,900 | $20,000 | $100.00 – $59,644 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Survey | ls | 238 | $18,350 | $1,100,000 | $250.00 – $3,500,000 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Remove Sign Less Than 20 Square Feet | each | 213 | $110.00 | $74.95 | $37.25 – $500.00 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Sign Post P2 | each | 203 | $150.00 | $212.00 | $67.00 – $600.00 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Pavement Marking Paint | gallon | 202 | $59.35 | $48.00 | $32.00 – $3,750 | Sep 22, 2026, Open the source page, project F-0006(269)262 ↗ |
| Small Sign Tubular Steel Post Base (B1) | each | 194 | $325.00 | $265.00 | $37.00 – $1,300 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Slipbase Sign Base (B3) | each | 159 | $540.00 | $432.00 | $191.00 – $11,600 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Pavement Message (Preformed Thermoplastic) | each | 156 | $295.00 | $525.00 | $12.70 – $3,325 | Sep 22, 2026, Open the source page, project F-0006(269)262 ↗ |
| Hot mix asphalt - 1/2 inch | ton | 140 | $178.00 | $95.80 | $65.00 – $1,200 | Sep 15, 2026, Open the source page, project F-R199(403) ↗ |
| Relocate Sign Less Than 20 Square Feet | each | 129 | $190.00 | $300.00 | $74.50 – $575.00 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Emulsified Asphalt (Tack) | ton | 126 | — | $1,588 | $0.01 – $5,540 | Sep 22, 2026, Open the source page, project F-0006(269)262 ↗ |
| Sign Post P3 | each | 117 | $220.00 | $225.00 | $125.00 – $560.00 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Reinforced steel - coated (plan quantity) | pound | 116 | $1.85 | $1.52 | $0.55 – $29.00 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Reconstruct Manhole | each | 114 | $818.00 | $1,428 | $290.00 – $3,300 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Concrete Drainage Structure 4 FT Wide x | each | 104 | $9,461 | $13,575 | $5,220 – $37,450 | Aug 25, 2026, Open the source page, project S-I15-1(143)17 ↗ |
| Remove Catch Basin | each | 66 | $1,248 | $1,530 | $252.00 – $4,250 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Remove Concrete (Curb and Gutter) | linear foot | 40 | $10.62 | $1.63 | $1.63 – $240.00 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Pavement Message Paint | square foot | 37 | $82.50 | $61.20 | $21.00 – $601.00 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Traffic Signal System | ls | 33 | — | $9,800 | $1,650 – $300,000 | May 28, 2026, Open the source page, project F-0089(649)416 ↗ |
| Structure concrete | cubic yard | 22 | $321,141 | $1,125,147 | $37,150 – $1,125,147 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Remove Pipe | linear foot | 21 | $50.00 | $18.36 | $10.50 – $430.00 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Traffic Control | ls | 17 | $71,000 | $226,000 | $5,202 – $523,000 | Sep 3, 2026, Open the source page, project F-0089(619)48 ↗ |
| Remove Fence | linear foot | 12 | $10.00 | $9.44 | $1.65 – $40.00 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Emulsified asphalt course-2p | ton | 8 | $807.50 | $850.00 | $765.00 – $1,155 | Sep 17, 2026, Open the source page, project F-0189(97)20 ↗ |
| Remove Guardrail | linear foot | 8 | $2.95 | $5.25 | $2.10 – $5.25 | Sep 22, 2026, Open the source page, project F-0006(269)262 ↗ |
| W-beam Guardrail | linear foot | 8 | $92.05 | $37.00 | $37.00 – $350.00 | Sep 10, 2026, Open the source page, project F-0040(254)6 ↗ |
| Relocate Fire Hydrant | each | 7 | $8,300 | $4,705 | $2,050 – $11,170 | Jun 18, 2026, Open the source page, project S-TR02(4) ↗ |
| Remove Manhole | each | 7 | $1,530 | $1,530 | $695.00 – $2,104 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Remove Fire Hydrant | each | 6 | $1,355 | $2,244 | $550.00 – $6,981 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Crack seal | pound | 5 | $6.50 | $7.00 | $0.66 – $7.40 | Jan 8, 2026, Open the source page, project F-I15-7(386)294 ↗ |
| Relocate Water Meter | each | 5 | $4,182 | $4,182 | $1,961 – $7,200 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Concrete Collar | each | 5 | $669.00 | $3,700 | $360.00 – $3,700 | May 7, 2026, Open the source page, project F-1826(5)4 ↗ |
| 12 inch gate valve | each | 4 | — | $6,403 | $6,162 – $6,403 | Apr 17, 2025, Open the source page, project F-0189(81)1 ↗ |
| Remove Crash Cushion | each | 4 | — | $529.00 | $529.00 – $713.00 | Nov 4, 2025, Open the source page, project F-0006(231)195 ↗ |
| Silt Fence | linear foot | 4 | — | $3.60 | $3.60 – $6.00 | Sep 30, 2025, Open the source page, project F-R199(319)5 ↗ |
| 3 inch conduit | linear foot | 3 | — | $9.56 | $9.56 – $25.00 | Apr 7, 2026, Open the source page, project F-ST99(1012) ↗ |
| Settlement Plate | each | 3 | — | $1,664 | $1,664 – $6,299 | Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗ |
| Granular Borrow | cubic yard | 3 | — | $390.00 | $23.27 – $390.00 | Oct 2, 2025, Open the source page, project F-0056(22)25 ↗ |
| Concrete Curb & Gutter, Type E | linear foot | 3 | — | $44.49 | $44.49 – $73.16 | Jan 22, 2026, Open the source page, project F-I15-6(276)1 ↗ |
| Remove Cable | linear foot | 3 | — | $0.68 | $0.5 – $0.68 | Sep 4, 2025, Open the source page, project F-ST99(958) ↗ |