Agency · awarded bid prices

Utah DOT: awarded unit prices

2,850 winning bid prices read from 289 source documents, 2024–2026. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › Utah DOT

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Public information servicels244$2,900$20,000$100.00 – $59,644Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Surveyls238$18,350$1,100,000$250.00 – $3,500,000Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Remove Sign Less Than 20 Square Feeteach213$110.00$74.95$37.25 – $500.00Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Sign Post P2each203$150.00$212.00$67.00 – $600.00Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Pavement Marking Paintgallon202$59.35$48.00$32.00 – $3,750Sep 22, 2026, Open the source page, project F-0006(269)262 ↗
Small Sign Tubular Steel Post Base (B1)each194$325.00$265.00$37.00 – $1,300Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Slipbase Sign Base (B3)each159$540.00$432.00$191.00 – $11,600Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Pavement Message (Preformed Thermoplastic)each156$295.00$525.00$12.70 – $3,325Sep 22, 2026, Open the source page, project F-0006(269)262 ↗
Hot mix asphalt - 1/2 inchton140$178.00$95.80$65.00 – $1,200Sep 15, 2026, Open the source page, project F-R199(403) ↗
Relocate Sign Less Than 20 Square Feeteach129$190.00$300.00$74.50 – $575.00Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Emulsified Asphalt (Tack)ton126—$1,588$0.01 – $5,540Sep 22, 2026, Open the source page, project F-0006(269)262 ↗
Sign Post P3each117$220.00$225.00$125.00 – $560.00Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Reinforced steel - coated (plan quantity)pound116$1.85$1.52$0.55 – $29.00Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Reconstruct Manholeeach114$818.00$1,428$290.00 – $3,300Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Concrete Drainage Structure 4 FT Wide xeach104$9,461$13,575$5,220 – $37,450Aug 25, 2026, Open the source page, project S-I15-1(143)17 ↗
Remove Catch Basineach66$1,248$1,530$252.00 – $4,250Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Remove Concrete (Curb and Gutter)linear foot40$10.62$1.63$1.63 – $240.00Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Pavement Message Paintsquare foot37$82.50$61.20$21.00 – $601.00Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Traffic Signal Systemls33—$9,800$1,650 – $300,000May 28, 2026, Open the source page, project F-0089(649)416 ↗
Structure concretecubic yard22$321,141$1,125,147$37,150 – $1,125,147Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Remove Pipelinear foot21$50.00$18.36$10.50 – $430.00Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Traffic Controlls17$71,000$226,000$5,202 – $523,000Sep 3, 2026, Open the source page, project F-0089(619)48 ↗
Remove Fencelinear foot12$10.00$9.44$1.65 – $40.00Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Emulsified asphalt course-2pton8$807.50$850.00$765.00 – $1,155Sep 17, 2026, Open the source page, project F-0189(97)20 ↗
Remove Guardraillinear foot8$2.95$5.25$2.10 – $5.25Sep 22, 2026, Open the source page, project F-0006(269)262 ↗
W-beam Guardraillinear foot8$92.05$37.00$37.00 – $350.00Sep 10, 2026, Open the source page, project F-0040(254)6 ↗
Relocate Fire Hydranteach7$8,300$4,705$2,050 – $11,170Jun 18, 2026, Open the source page, project S-TR02(4) ↗
Remove Manholeeach7$1,530$1,530$695.00 – $2,104Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Remove Fire Hydranteach6$1,355$2,244$550.00 – $6,981Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Crack sealpound5$6.50$7.00$0.66 – $7.40Jan 8, 2026, Open the source page, project F-I15-7(386)294 ↗
Relocate Water Metereach5$4,182$4,182$1,961 – $7,200Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Concrete Collareach5$669.00$3,700$360.00 – $3,700May 7, 2026, Open the source page, project F-1826(5)4 ↗
12 inch gate valveeach4—$6,403$6,162 – $6,403Apr 17, 2025, Open the source page, project F-0189(81)1 ↗
Remove Crash Cushioneach4—$529.00$529.00 – $713.00Nov 4, 2025, Open the source page, project F-0006(231)195 ↗
Silt Fencelinear foot4—$3.60$3.60 – $6.00Sep 30, 2025, Open the source page, project F-R199(319)5 ↗
3 inch conduitlinear foot3—$9.56$9.56 – $25.00Apr 7, 2026, Open the source page, project F-ST99(1012) ↗
Settlement Plateeach3—$1,664$1,664 – $6,299Sep 22, 2026, Open the source page, project F-I15-1(136)6 ↗
Granular Borrowcubic yard3—$390.00$23.27 – $390.00Oct 2, 2025, Open the source page, project F-0056(22)25 ↗
Concrete Curb & Gutter, Type Elinear foot3—$44.49$44.49 – $73.16Jan 22, 2026, Open the source page, project F-I15-6(276)1 ↗
Remove Cablelinear foot3—$0.68$0.5 – $0.68Sep 4, 2025, Open the source page, project F-ST99(958) ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.

More prices in Utah: statewide figures.