| 32 12 16.13 hot mix asphalt – 3/8 inch | ton | 2 | — | $103.00 | $95.00 – $103.00 | Jul 11, 2024, Open bid tab, 2024-eagles-landing ↗ |
| 32 01 16.71 Rotomilling – 2 ½ Inch | square foot | 2 | — | $0.33 | $0.32 – $0.33 | Jul 3, 2024, Open bid tab, 2024-5200-west ↗ |
| 32 11 23 Untreated Base Course | ton | 2 | — | $45.50 | $45.50 – $56.00 | Jul 11, 2024, Open bid tab, 2024-eagles-landing ↗ |
| 31 23 16 Roadway Excavation | cubic yard | 2 | — | $29.00 | $29.00 – $65.00 | Jul 11, 2024, Open bid tab, 2024-eagles-landing ↗ |
| 01 71 13 Mobilization and Demobilization | ls | 2 | — | $20,000 | $17,000 – $20,000 | Jul 11, 2024, Open bid tab, 2024-eagles-landing ↗ |
| 01 71 23 Construction Layout | ls | 2 | — | $8,000 | $8,000 – $9,500 | Jul 11, 2024, Open bid tab, 2024-eagles-landing ↗ |
| 01 57 00 Temporary Controls | ls | 2 | — | $6,350 | $6,350 – $16,500 | Jul 11, 2024, Open bid tab, 2024-eagles-landing ↗ |
| 01 55 26 Traffic Control | ls | 2 | — | $11,000 | $11,000 – $23,400 | Jul 11, 2024, Open bid tab, 2024-eagles-landing ↗ |
| 00 72 00 General Conditions | ls | 2 | — | $9,000 | $9,000 – $17,000 | Jul 11, 2024, Open bid tab, 2024-eagles-landing ↗ |
| Place Owner-Provided Concrete Barriers | ls | 1 | — | $2,621 | $2,621 | Dec 19, 2024, Open bid tab, 2024-santaquin-debris-basin ↗ |
| Remove and Place Sediment and Debris | cubic yard | 1 | — | $5.75 | $5.75 | Dec 19, 2024, Open bid tab, 2024-santaquin-debris-basin ↗ |
| 33 12 16 Raise and Collar Water Valve | each | 1 | — | $1,650 | $1,650 | Jul 11, 2024, Open bid tab, 2024-eagles-landing ↗ |
| 30 01 16.71 Rotomilling - 2 Inch | square foot | 1 | — | $0.38 | $0.38 | Jul 11, 2024, Open bid tab, 2024-eagles-landing ↗ |
| 30 05 13 Granular Borrow | ton | 1 | — | $28.50 | $28.50 | Jul 11, 2024, Open bid tab, 2024-eagles-landing ↗ |
| 32 01 05 Sign, Post, and Foundation | each | 1 | — | $1,300 | $1,300 | Jul 3, 2024, Open bid tab, 2024-5200-west ↗ |
| 31 05 10 Survey Monuments | each | 1 | — | $950.00 | $950.00 | Jul 3, 2024, Open bid tab, 2024-5200-west ↗ |
| 32 17 23 Railroad Pavement Marking | each | 1 | — | $350.00 | $350.00 | Jul 3, 2024, Open bid tab, 2024-5200-west ↗ |
| 32 17 23 Pavement Marking Paint | linear foot | 1 | — | $0.24 | $0.24 | Jul 3, 2024, Open bid tab, 2024-5200-west ↗ |
| 32 12 16.13 Asphalt Driveway | square foot | 1 | — | $7.95 | $7.95 | Jul 3, 2024, Open bid tab, 2024-5200-west ↗ |
| 32 12 16.13 hot mix asphalt – 3/8 inch leveling course | ton | 1 | — | $139.00 | $139.00 | Jul 3, 2024, Open bid tab, 2024-5200-west ↗ |
| 32 11 23 Gravel Driveway | square foot | 1 | — | $6.00 | $6.00 | Jul 3, 2024, Open bid tab, 2024-5200-west ↗ |
| 02 41 13 Remove Irrigation Structure | each | 1 | — | $2,500 | $2,500 | Jul 3, 2024, Open bid tab, 2024-5200-west ↗ |
| 31 11 00 tree and stump remove | each | 1 | — | $485.00 | $485.00 | Jul 3, 2024, Open bid tab, 2024-5200-west ↗ |
| 32 02 07 Relocate Mailbox | each | 1 | — | $1,600 | $1,600 | Jul 3, 2024, Open bid tab, 2024-5200-west ↗ |
| Environmental Protection | ls | 1 | — | $14,312 | $14,312 | Dec 19, 2024, Open bid tab, 2024-santaquin-debris-basin ↗ |
| Mobilization | ls | 1 | — | $11,040 | $11,040 | Dec 19, 2024, Open bid tab, 2024-santaquin-debris-basin ↗ |