| Tack Coat @0.10 Gal./S.Y. | gals | 23 | $3.00 | $2.50 | $0.01 – $3.50 | Jan 16, 2026, Open bid tab, bidtabinranfar2502pdf-s0 ↗ |
| 1-1/2 inch - 9.5mm hot mix asphalt surface, pg64-22 | ton | 20 | $98.50 | $105.00 | $94.80 – $111.55 | Jan 16, 2026, Open bid tab, bidtabinranfar2502pdf-s0 ↗ |
| Traffic Control Devices And Lighting, As Per Plan | ls | 16 | $600.00 | $600.00 | $500.00 – $2,000 | Jan 16, 2026, Open bid tab, bidtabinranfar2502pdf-s0 ↗ |
| Valve Adjusted To Grade | each | 15 | — | $1.00 | $1.00 – $295.75 | Jan 16, 2026, Open bid tab, bidtabinranfar2502pdf-s0 ↗ |
| 1-1/2 inch± asphalt milling | square yard | 15 | $2.00 | $2.00 | $0.74 – $5.00 | Jan 16, 2026, Open bid tab, bidtabinranfar2502pdf-s0 ↗ |
| Manhole Adjusted To Grade | each | 15 | — | $1.00 | $1.00 – $800.00 | Jan 16, 2026, Open bid tab, bidtabinranfar2502pdf-s0 ↗ |
| Line, Paint, Solid, White, Stop Line | linear foot | 4 | — | $10.20 | $10.20 – $11.75 | Jan 16, 2026, Open bid tab, bidtabinranfar2502pdf-s0 ↗ |
| Remove, as per plan | ls | 4 | — | $3,000 | $200.00 – $3,000 | Jan 16, 2026, Open bid tab, bidtabinranfar2502pdf-s1 ↗ |
| Maintaining Traffic | ls | 4 | — | $1,000 | $250.00 – $1,000 | Feb 18, 2020, Open bid tab, bidtabinranfar1901pdf-s0 ↗ |
| 2-1/2 inch - qc/qa-hot mix asphalt, 2, 64, intermediate 19.5mm | ton | 3 | — | $91.00 | $91.00 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s0 ↗ |
| 1-1/2 inch - qc/qa-hot mix asphalt, 2, 64, surface 9.5mm | ton | 3 | — | $91.00 | $91.00 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s0 ↗ |
| Traffic Controls For Construction And Maintenance Operations, As Per Plan | ls | 3 | — | $200.00 | $200.00 – $500.00 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s0 ↗ |
| Mulched Seeding, Grass, Type 2, As Per Plan | square yard | 3 | — | $2.50 | $2.50 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s0 ↗ |
| Subgrade Treatment, Type 1A, As Per Plan | square yard | 3 | — | $2.00 | $2.00 – $2.50 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s0 ↗ |
| Compaction aggreagte, no. 53, base | ton | 2 | — | $27.00 | $27.00 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s0 ↗ |
| Pavement remove, asphalt | square yard | 2 | — | $5.25 | $5.25 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s0 ↗ |
| Compaction aggregate, no. 53, base | ton | 2 | — | $75.00 | $27.00 – $75.00 | Jan 16, 2026, Open bid tab, bidtabinranfar2502pdf-s1 ↗ |
| Subgrade Treatement, Type 1A | square yard | 1 | — | $2.50 | $2.50 | Jan 16, 2026, Open bid tab, bidtabinranfar2502pdf-s1 ↗ |
| Excavation, Common | c.y | 1 | — | $78.00 | $78.00 | Jan 16, 2026, Open bid tab, bidtabinranfar2502pdf-s1 ↗ |
| Catch Basin, Type K Double Wide, As Per Plan | each | 1 | — | $9,250 | $9,250 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s2 ↗ |
| Pipe, type 2, circular, 30 inch 907.23 | linear foot | 1 | — | $100.00 | $100.00 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s2 ↗ |
| Pccp for approaches, 6 inch, as per plan | square yard | 1 | — | $85.00 | $85.00 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s2 ↗ |
| Combination Curb And Gutter, | linear foot | 1 | — | $30.00 | $30.00 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s2 ↗ |
| Concrete, Curb Ramp | s.f | 1 | — | $30.00 | $30.00 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s2 ↗ |
| Sidewalk, Concrete, As Per Plan | s.f | 1 | — | $8.50 | $8.50 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s2 ↗ |
| Pavement, Concrete Removed, Sidewalk | square yard | 1 | — | $3.00 | $3.00 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s2 ↗ |
| Remove, curb and gutter | linear foot | 1 | — | $1.75 | $1.75 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s2 ↗ |
| Morris street (alley @ park to williams street full reconstruct) 110 mobilization and demobilization | ls | 1 | — | $1,500 | $1,500 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s2 ↗ |
| Hickory Street (West Lane 211 Hickory To Williams Street) 110 Mobilization And Demobilization | ls | 1 | — | $750.00 | $750.00 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s1 ↗ |
| Pursley Street(Hickory Street To Olive Street) 110 Mobilization And Demobilization | ls | 1 | — | $100.00 | $100.00 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s0 ↗ |
| 1-1/2 inch - 12.5mm hot mix asphalt intermediate, pg64-22 | ton | 1 | — | $95.00 | $95.00 | Feb 18, 2020, Open bid tab, bidtabinranfar1901pdf-s2 ↗ |
| Mulched Seeding, Grass, Type 2 | square yard | 1 | — | $5.50 | $5.50 | Jan 16, 2026, Open bid tab, bidtabinranfar2502pdf-s1 ↗ |
| 3 inch 25mm, type b, hot mix asphalt base, pg 64-22 | ton | 1 | — | $165.00 | $165.00 | Jan 16, 2026, Open bid tab, bidtabinranfar2502pdf-s1 ↗ |
| Geogrid Type 1B, As Per Plan | square yard | 1 | — | $2.25 | $2.25 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s2 ↗ |
| Sign, Sheet Assembly, Remove And Relocate | each | 1 | — | $200.00 | $200.00 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s2 ↗ |
| 2-1/2 inch 19.5 mm, type b, hot mix asphalt intermediate, pg 64-22 | ton | 1 | — | $182.00 | $182.00 | Jan 16, 2026, Open bid tab, bidtabinranfar2502pdf-s1 ↗ |
| Subgrade Treatment, Type 1C, As Per Plan | square yard | 1 | — | $22.50 | $22.50 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s2 ↗ |
| Pipe, type 2, circular, 12 inch 907.23 | linear foot | 1 | — | $50.00 | $50.00 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s2 ↗ |
| Pipe, type 2, circular, 8 inch 907.23 | linear foot | 1 | — | $30.00 | $30.00 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s2 ↗ |
| Pipe, type 2, circular, 6 inch 907.23 | linear foot | 1 | — | $25.00 | $25.00 | Feb 15, 2022, Open bid tab, bidtabinranfar2102pdf-s2 ↗ |