Old Orchard Beach, ME: awarded unit prices

27 winning bid prices read from 1 source documents, 2023. The table lists the 27 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › Old Orchard Beach, ME

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Supply and install of 6”underdrainlinear foot1—$54.00$54.00Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Protect Existing Utility Poleseach1—$1,500$1,500Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Existing Water Main Relocationls1—$8,500$8,500Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Existing Sewer Relocationls1—$25,000$25,000Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Driveway pavement (9.0 mm hot mix asphalt, 3”)ton1—$540.00$540.00Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Loam and Seedls1—$9,810$9,810Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Restoration of Existing Sidewalkls1—$1,580$1,580Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Trench paving (19.0 mm hot mix asphalt binder, 2.25 inch)ton1—$200.00$200.00Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Remove of existing pavement (trench and entire width of bower lane)square yard1—$25.00$25.00Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Surface paving on bower lane (12.5 mm hot mix asphalt wearing, 1.5 inch)ton1—$200.00$200.00Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Binder paving on bower lane (19.0 mm hot mix asphalt binder, 2.25”)ton1—$150.00$150.00Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Aggregate Subbase (MDOT Type A Gravel - Bower Lane)cubic yard1—$75.00$75.00Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Aggregate Base (MDOT Type D Gravel - Bower Lane)cubic yard1—$60.00$60.00Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Milling, shim and overlay with 1.5” wearing course (goldenrod street & balsam lane)square yard1—$30.00$30.00Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Replace existing 4’ diameter catch basin on saco ave with 6’ diameter catch basinls1—$9,800$9,800Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Modify Leaching Catch Basinseach1—$1,250$1,250Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Supply & install of 4’ diameter leaching catch basinseach1—$11,600$11,600Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Supply & install of 6’ diameter leaching catch basinseach1—$14,600$14,600Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Supply & install of 4’ catch basinseach1—$4,500$4,500Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Supply & install of 12” hdpe storm drainlinear foot1—$140.00$140.00Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Supply & install of 15” hdpe storm drainlinear foot1—$122.00$122.00Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Replace of unsuitable materialcubic yard1—$25.00$25.00Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Traffic Control and Regulationls1—$48,540$48,540Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Mobilization/Demobilization (7.5% Max of Total Bid)ls1—$35,075$35,075Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Test Pit Excavation and Backfilleach1—$1,200$1,200Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Erosion and sediment controlls1—$7,060$7,060Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗
Stump removeeach1—$750.00$750.00Jan 26, 2023, Open bid tab, Balsam Ln, Goldenrod St & Bower Ln Drainage Improvem ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.

More prices in Maine: statewide figures.