| Mobilization | u | 196 | — | $60,000 | $1,000 – $5,900,000 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Maintenance Of Traffic | u | 164 | — | $50,000 | $500.00 – $400,000 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Uniformed Officers With Vehicle | $ | 161 | — | $120,000 | $1,600 – $600,000 | Jan 8, 2009, Open bid tab, X-A000(727), 15382 ↗ |
| Flaggers | hour | 143 | $20.00 | $24.00 | $1.00 – $35.00 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Miscellaneous Temporary Erosion And Sediment Control | $ | 129 | — | $10,800 | $1,000 – $100,000 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Fuel adjust | $ | 116 | $20,000 | $10,000 | $2,000 – $500,000 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Hot asphalt pavement, hand method | ton | 114 | $105.00 | $125.00 | $50.00 – $500.00 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Asphalt cement adjust | $ | 104 | $20,000 | $1,000 | $500.00 – $75,000 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Alterations And Additions As Needed- Unanticipated Work | $ | 96 | $5,000 | $15,000 | $500.00 – $50,000 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Storm Water Pollution Prevention Plan | u | 90 | $3,350 | $5,000 | $1,200 – $27,000 | Jan 8, 2009, Open bid tab, X-A000(727), 15382 ↗ |
| Silt Fence | linear foot | 90 | $3.00 | $5.00 | $0.5 – $10.00 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Portable Changeable Message Sign | u | 86 | $7,100 | $7,000 | $400.00 – $25,000 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Single Delineator With Post | each | 84 | $30.00 | $30.00 | $19.00 – $40.00 | Jan 8, 2009, Open bid tab, X-A000(727), 15382 ↗ |
| Cold milling asphalt surfaces | square yard | 82 | $6.12 | $3.00 | $1.10 – $72.00 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Sawed asphalt pavement | linear foot | 81 | $2.00 | $2.00 | $1.00 – $10.00 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Demolishing Buildings | u | 81 | $10,000 | $3,300 | $1,000 – $120,000 | Sep 25, 2008, Open bid tab, HP-STP-F-X-0351(008), P2953 ↗ |
| Polyethylene Liner | each | 79 | $200.00 | $200.00 | $96.50 – $450.00 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Fine Grading | u | 79 | — | $40,000 | $1,200 – $196,000 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Erosion Stone | ton | 79 | $30.00 | $20.00 | $15.00 – $100.00 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Common Excavation | cubic yard | 77 | $10.00 | $16.00 | $3.60 – $100.00 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Retroreflective Beam Guardrail Delineator | each | 76 | $5.00 | $4.30 | $4.00 – $10.00 | Jan 8, 2009, Open bid tab, X-A000(727), 15382 ↗ |
| Common Structure Excavation Exploratory | cubic yard | 73 | $46.00 | $40.00 | $5.00 – $500.00 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Crushed Gravel For Shoulder Leveling | ton | 72 | $22.00 | $17.50 | $1.00 – $70.00 | Jan 8, 2009, Open bid tab, X-A000(727), 15382 ↗ |
| Monitoring Swppp And Erosion And Sediment Controls | hour | 72 | $65.00 | $150.00 | $1.00 – $200.00 | Jan 8, 2009, Open bid tab, X-A000(727), 15382 ↗ |
| Retroreflective paint pavement. marking, 4 inch line | linear foot | 71 | $0.13 | $0.14 | $0.08 – $1.00 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Steel Witness Markers | each | 67 | $25.00 | $25.00 | $20.00 – $125.00 | Sep 25, 2008, Open bid tab, HP-STP-F-X-0351(008), P2953 ↗ |
| Remove of existing bridge structure | u | 66 | — | $26,500 | $6,000 – $800,000 | Jan 8, 2009, Open bid tab, X-A000(727), 15382 ↗ |
| Humus | cubic yard | 65 | $22.00 | $65.00 | $0.16 – $200.00 | Jan 8, 2009, Open bid tab, X-A000(727), 15382 ↗ |
| Catch Basins Type B | u | 63 | $1,700 | $2,500 | $1,200 – $3,350 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Remove of guardrail (f) | linear foot | 62 | $2.50 | $1.25 | $1.00 – $18.00 | Jan 8, 2009, Open bid tab, X-A000(727), 15382 ↗ |
| Cofferdams | u | 61 | $55,000 | $5,000 | $1.00 – $1,004,000 | Sep 11, 2008, Open bid tab, MGS-BRF-X-T-0221(010), 13269 ↗ |
| Stone Fill, Class C | cubic yard | 60 | $41.50 | $50.00 | $23.00 – $150.00 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Beam guardrail (standard section- wood post) | linear foot | 58 | $18.42 | $21.00 | $11.00 – $43.75 | Oct 23, 2008, Open bid tab, X-A000(729), 15389 ↗ |
| Hot asphalt pavement, machine method | ton | 55 | $63.00 | $92.00 | $38.00 – $280.00 | Oct 9, 2008, Open bid tab, BHF-T-0101(015), 13678 ↗ |
| Quality Control Quality Assurance (Qc/Qa Asphalt | $ | 54 | — | $78,000 | $1,500 – $167,300 | Jan 8, 2009, Open bid tab, X-A000(727), 15382 ↗ |
| Traffic Sign Type C (F) | square foot | 53 | $40.00 | $50.00 | $20.00 – $120.00 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Repairs Or Replacements As Needed | $ | 52 | $10,000 | $10,000 | $1,000 – $300,000 | Jan 8, 2009, Open bid tab, X-A000(727), 15382 ↗ |
| Retroreflect. thermoplas. pavement. marking, 18 inch line | linear foot | 52 | $3.00 | $2.35 | $1.10 – $40.00 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |
| Relocating Traffic Sign, Type C | u | 52 | $182.50 | $150.00 | $75.00 – $1,850 | Oct 9, 2008, Open bid tab, BHF-T-0101(015), 13678 ↗ |
| Temporary asphalt pavement | ton | 52 | $80.00 | $100.00 | $43.10 – $200.00 | Jan 8, 2009, Open bid tab, MGS-STP-X-5119(007), 13249 ↗ |