ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Traffic Maintenancels8$23,250$21,500$5,300 – $66,000May 13, 2025, Open bid tab, 2025C021 ↗
Construction Survey Measurementls7$18,000$88,640$5,750 – $88,640May 13, 2025, Open bid tab, 2025C021 ↗
Storm Water Pollution Prevention Plan (Type 3)ls6—$41,000$500.00 – $41,000May 13, 2025, Open bid tab, 2025C021 ↗
Two-Person Survey Crewhour6$262.50$0.01$0.01 – $330.00May 13, 2025, Open bid tab, 2025C021 ↗
Clearing and Grubbingls5—$7,500$5,000 – $90,000May 13, 2025, Open bid tab, 2025C021 ↗
Leveling Courseton5$30.00$38.00$28.00 – $75.00May 13, 2025, Open bid tab, 2025C021 ↗
Seeding (Schedule A)msf4—$580.00$330.00 – $580.00May 13, 2025, Open bid tab, 2025C021 ↗
Topsoil, 4 inch deepmsf4—$1,055$400.00 – $1,055May 13, 2025, Open bid tab, 2025C021 ↗
Classified Fill and Backfill (Type II-A)ton4—$28.00$15.00 – $28.00May 13, 2025, Open bid tab, 2025C021 ↗
Dewateringls4—$27,500$6,000 – $100,000May 13, 2025, Open bid tab, 2025C021 ↗
Standard Signsquare foot4—$185.00$66.00 – $185.00May 13, 2025, Open bid tab, 2025C021 ↗
Unusable Excavationcubic yard3—$28.00$8.00 – $28.00Jun 26, 2019, Open bid tab, 2019C056 ↗
Remove Curb and Gutterlinear foot3—$8.00$5.00 – $8.00Jun 26, 2019, Open bid tab, 2019C056 ↗
Temporary Group Mailboxesls3—$3,500$600.00 – $6,500May 13, 2025, Open bid tab, 2025C021 ↗
Remove AND Reset Fencelinear foot3—$137.00$37.00 – $137.00May 13, 2025, Open bid tab, 2025C021 ↗
Remove and Replace Valve Box Top Sectioneach3—$1,435$400.00 – $1,435May 13, 2025, Open bid tab, 2025C021 ↗
A.C. Pavement (Class E)ton3—$150.00$95.00 – $150.00May 13, 2025, Open bid tab, 2025C021 ↗
P.C.C. Curb and Gutter (All Types)linear foot3—$36.00$27.00 – $36.00May 13, 2025, Open bid tab, 2025C021 ↗
Insulation Board (R-9)square foot3—$3.00$2.00 – $3.00May 13, 2025, Open bid tab, 2025C021 ↗
Geotextile (Type A)square yard3—$1.25$1.00 – $2.00May 13, 2025, Open bid tab, 2025C021 ↗
Classified Fill and Backfill (Type II)ton3—$28.00$14.75 – $28.00May 13, 2025, Open bid tab, 2025C021 ↗
Remove Bollardeach2—$25.00$25.00 – $150.00Jun 26, 2019, Open bid tab, 2019C056 ↗
Remove and relocate signeach2—$1,000$350.00 – $1,000May 5, 2017, Open bid tab, 2017C019 ↗
Adjust Storm Drain Manhole Ringeach2—$190.00$190.00 – $1,000Jun 26, 2019, Open bid tab, 2019C056 ↗
Remove and Replace Manhole Grade Ringseach2—$225.00$225.00 – $1,000Jun 26, 2019, Open bid tab, 2019C056 ↗
Reconstruct Driveway, Asphalt (Class E)square yard2—$91.00$60.00 – $91.00Sep 27, 2016, Open bid tab, 2016C077 ↗
Usable Excavationcubic yard2—$9.00$9.00 – $21.00Mar 2, 2016, Open bid tab, 2016C005 ↗
Remove Pavementsquare yard2—$2.00$2.00 – $3.00May 5, 2017, Open bid tab, 2017C019 ↗
Relocate Mailboxeach2—$180.00$180.00 – $325.00May 13, 2025, Open bid tab, 2025C021 ↗
Temporary fencelinear foot2—$15.75$3.50 – $15.75May 13, 2025, Open bid tab, 2025C021 ↗
Remove Fencelinear foot2—$74.00$3.25 – $74.00May 13, 2025, Open bid tab, 2025C021 ↗
Root Pruninglinear foot2—$21.00$2.50 – $21.00May 13, 2025, Open bid tab, 2025C021 ↗
Salvage and Relocate or Dispose Existing Bouldereach2—$385.00$130.00 – $385.00May 13, 2025, Open bid tab, 2025C021 ↗
Adjust Key Boxeach2—$470.00$300.00 – $470.00May 13, 2025, Open bid tab, 2025C021 ↗
Remove and Replace Manhole Cover and Frameeach2—$960.00$800.00 – $960.00May 13, 2025, Open bid tab, 2025C021 ↗
Remove and Replace Manhole Cone Sectioneach2—$2,800$1,500 – $2,800May 13, 2025, Open bid tab, 2025C021 ↗
P.c.c. curb ramp (6 inch thick)each2—$3,400$3,200 – $3,400May 13, 2025, Open bid tab, 2025C021 ↗
P.c.c. sidewalk (6 inch thick, standard finish)square yard2—$113.00$80.00 – $113.00May 13, 2025, Open bid tab, 2025C021 ↗
P.c.c. sidewalk (4 inch thick, standard finish)square yard2—$77.00$56.00 – $77.00May 13, 2025, Open bid tab, 2025C021 ↗
Insulation Board (R-4.5)square foot2—$1.75$1.00 – $1.75May 13, 2025, Open bid tab, 2025C021 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.