| Traffic Maintenance | ls | 8 | $23,250 | $21,500 | $5,300 – $66,000 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Construction Survey Measurement | ls | 7 | $18,000 | $88,640 | $5,750 – $88,640 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Storm Water Pollution Prevention Plan (Type 3) | ls | 6 | — | $41,000 | $500.00 – $41,000 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Two-Person Survey Crew | hour | 6 | $262.50 | $0.01 | $0.01 – $330.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Clearing and Grubbing | ls | 5 | — | $7,500 | $5,000 – $90,000 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Leveling Course | ton | 5 | $30.00 | $38.00 | $28.00 – $75.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Seeding (Schedule A) | msf | 4 | — | $580.00 | $330.00 – $580.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Topsoil, 4 inch deep | msf | 4 | — | $1,055 | $400.00 – $1,055 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Classified Fill and Backfill (Type II-A) | ton | 4 | — | $28.00 | $15.00 – $28.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Dewatering | ls | 4 | — | $27,500 | $6,000 – $100,000 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Standard Sign | square foot | 4 | — | $185.00 | $66.00 – $185.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Unusable Excavation | cubic yard | 3 | — | $28.00 | $8.00 – $28.00 | Jun 26, 2019, Open bid tab, 2019C056 ↗ |
| Remove Curb and Gutter | linear foot | 3 | — | $8.00 | $5.00 – $8.00 | Jun 26, 2019, Open bid tab, 2019C056 ↗ |
| Temporary Group Mailboxes | ls | 3 | — | $3,500 | $600.00 – $6,500 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Remove AND Reset Fence | linear foot | 3 | — | $137.00 | $37.00 – $137.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Remove and Replace Valve Box Top Section | each | 3 | — | $1,435 | $400.00 – $1,435 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| A.C. Pavement (Class E) | ton | 3 | — | $150.00 | $95.00 – $150.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| P.C.C. Curb and Gutter (All Types) | linear foot | 3 | — | $36.00 | $27.00 – $36.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Insulation Board (R-9) | square foot | 3 | — | $3.00 | $2.00 – $3.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Geotextile (Type A) | square yard | 3 | — | $1.25 | $1.00 – $2.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Classified Fill and Backfill (Type II) | ton | 3 | — | $28.00 | $14.75 – $28.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Remove Bollard | each | 2 | — | $25.00 | $25.00 – $150.00 | Jun 26, 2019, Open bid tab, 2019C056 ↗ |
| Remove and relocate sign | each | 2 | — | $1,000 | $350.00 – $1,000 | May 5, 2017, Open bid tab, 2017C019 ↗ |
| Adjust Storm Drain Manhole Ring | each | 2 | — | $190.00 | $190.00 – $1,000 | Jun 26, 2019, Open bid tab, 2019C056 ↗ |
| Remove and Replace Manhole Grade Rings | each | 2 | — | $225.00 | $225.00 – $1,000 | Jun 26, 2019, Open bid tab, 2019C056 ↗ |
| Reconstruct Driveway, Asphalt (Class E) | square yard | 2 | — | $91.00 | $60.00 – $91.00 | Sep 27, 2016, Open bid tab, 2016C077 ↗ |
| Usable Excavation | cubic yard | 2 | — | $9.00 | $9.00 – $21.00 | Mar 2, 2016, Open bid tab, 2016C005 ↗ |
| Remove Pavement | square yard | 2 | — | $2.00 | $2.00 – $3.00 | May 5, 2017, Open bid tab, 2017C019 ↗ |
| Relocate Mailbox | each | 2 | — | $180.00 | $180.00 – $325.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Temporary fence | linear foot | 2 | — | $15.75 | $3.50 – $15.75 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Remove Fence | linear foot | 2 | — | $74.00 | $3.25 – $74.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Root Pruning | linear foot | 2 | — | $21.00 | $2.50 – $21.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Salvage and Relocate or Dispose Existing Boulder | each | 2 | — | $385.00 | $130.00 – $385.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Adjust Key Box | each | 2 | — | $470.00 | $300.00 – $470.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Remove and Replace Manhole Cover and Frame | each | 2 | — | $960.00 | $800.00 – $960.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Remove and Replace Manhole Cone Section | each | 2 | — | $2,800 | $1,500 – $2,800 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| P.c.c. curb ramp (6 inch thick) | each | 2 | — | $3,400 | $3,200 – $3,400 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| P.c.c. sidewalk (6 inch thick, standard finish) | square yard | 2 | — | $113.00 | $80.00 – $113.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| P.c.c. sidewalk (4 inch thick, standard finish) | square yard | 2 | — | $77.00 | $56.00 – $77.00 | May 13, 2025, Open bid tab, 2025C021 ↗ |
| Insulation Board (R-4.5) | square foot | 2 | — | $1.75 | $1.00 – $1.75 | May 13, 2025, Open bid tab, 2025C021 ↗ |