| Mobilization | ls | 1,232 | — | $290,000 | $0.01 – $9,059,000 | Sep 30, 2026, line 0390 ↗ |
| Construction sign | square foot | 1,047 | $15.00 | $10.00 | $0.01 – $250.00 | Sep 30, 2026, line 0340 ↗ |
| Cone | each | 1,034 | $20.00 | $20.00 | $0.01 – $421.04 | Sep 30, 2026, line 0330 ↗ |
| Flagger | hour | 1,031 | $33.00 | $0.01 | $0.01 – $215.44 | Sep 30, 2026, line 0360 ↗ |
| Temporary Soil Erosion and Water Pollution Control | ls | 1,026 | — | $50,000 | $0.01 – $1,250,000 | Sep 30, 2026, line 0380 ↗ |
| Hand Labor, Straight Time | hour | 956 | $45.00 | $50.00 | $0.01 – $256.00 | Sep 30, 2026, line 0270 ↗ |
| Drum | each | 919 | $50.00 | $100.00 | $0.01 – $179.38 | Sep 30, 2026, line 0320 ↗ |
| Truck - Large (Including Operator) | hour | 906 | $90.00 | $140.00 | $0.01 – $500.00 | Sep 30, 2026, line 0300 ↗ |
| All Purpose Excavator (Including Operator) | hour | 900 | $150.00 | $235.00 | $0.01 – $500.00 | Sep 30, 2026, line 0280 ↗ |
| Asphalt tack coat - applied | g | 895 | $10.00 | $10.00 | $1.00 – $223.00 | Sep 30, 2026, line 0070 ↗ |
| Maintenance of Traffic Control Devices | cd | 876 | — | $1,000 | $0.01 – $1,950,000 | Sep 30, 2026, line 0350 ↗ |
| 4 inch white or yellow paint pavement marking line | linear foot | 718 | — | $0.13 | $0.01 – $15.00 | Sep 30, 2026, line 0240 ↗ |
| Mulching | unit | 667 | $42.65 | $40.00 | $1.00 – $5,000 | Sep 30, 2026, line 0230 ↗ |
| Hot mix asphalt 9.5 mm (sidewalk, drives, incidentals) | ton | 610 | $219.50 | $350.00 | $0.01 – $1,000 | Sep 30, 2026, line 0040 ↗ |
| Common Excavation | cubic yard | 552 | $24.00 | $45.00 | $0.01 – $500.00 | Sep 30, 2026, line 0030 ↗ |
| Plain Riprap | cubic yard | 541 | $83.00 | $68.25 | $1.00 – $594.50 | Sep 23, 2026, line 0270 ↗ |
| Loam | cubic yard | 538 | $62.00 | $160.00 | $1.00 – $1,000 | Sep 30, 2026, line 0260 ↗ |
| Seeding Method Number 2 | unit | 529 | $45.00 | $1.00 | $1.00 – $3,000 | Sep 30, 2026, line 0220 ↗ |
| Hot MIX Asphalt 12.5 MM Base | ton | 522 | $195.00 | $200.00 | $66.50 – $800.00 | Sep 30, 2026, line 0060 ↗ |
| Remove pavement surface | square yard | 515 | $12.00 | $38.00 | $0.01 – $500.00 | Sep 16, 2026, line 0010 ↗ |
| Aggregate Subbase Course - Gravel | cubic yard | 499 | $45.00 | $65.00 | $1.00 – $850.00 | Sep 30, 2026, line 0090 ↗ |
| Pavement butt joint | square yard | 493 | $14.28 | $30.00 | $0.01 – $100.00 | Sep 30, 2026, line 0020 ↗ |
| Erosion Control Geotextile | square yard | 492 | $4.00 | $4.25 | $1.00 – $100.00 | Sep 30, 2026, line 0310 ↗ |
| Temporary 4 inch paint pavement marking line, white or yellow | linear foot | 482 | $0.15 | $0.13 | $0.01 – $12.00 | Sep 30, 2026, line 0260 ↗ |
| Field Office Type B | each | 475 | $8,500 | $25,000 | $1.00 – $76,000 | Sep 30, 2026, line 0370 ↗ |
| Erosion Control Blanket | square yard | 475 | $4.00 | $4.00 | $0.74 – $55.00 | Sep 30, 2026, line 0250 ↗ |
| Reflectorized Flexible Guardrail Marker | each | 473 | $52.50 | $50.00 | $1.00 – $320.00 | Sep 30, 2026, line 0200 ↗ |
| White or Yellow Pavement & Curb Marking | square foot | 464 | $2.52 | $5.00 | $0.58 – $20.00 | Sep 30, 2026, line 0250 ↗ |
| Portable Changeable Message Sign | each | 458 | $3,600 | $3,000 | $1.00 – $33,900 | Sep 30, 2026, line 0370 ↗ |
| Hot MIX Asphalt (Shimming) | ton | 438 | $121.00 | $240.00 | $64.00 – $990.00 | Aug 5, 2026, line 0040 ↗ |
| Granular Borrow | cubic yard | 361 | $40.00 | $75.00 | $0.01 – $597.00 | Sep 30, 2026, line 0050 ↗ |
| Type III Barricade | each | 358 | $200.00 | $180.00 | $0.01 – $30,000 | Sep 30, 2026, line 0380 ↗ |
| Curb Type 3 | linear foot | 319 | $24.00 | $25.00 | $4.90 – $300.00 | Jun 17, 2026, line 0110 ↗ |
| Adjusting Manhole or Catch Basin to Grade | each | 293 | $1,500 | $2,500 | $130.00 – $5,250 | Sep 30, 2026, line 0180 ↗ |
| Hot mix asphalt 12.5 mm hot mix asphalt surface | ton | 290 | $190.00 | $245.00 | $64.84 – $1,000 | Sep 30, 2026, line 0100 ↗ |
| Erosion Control MIX | cubic yard | 283 | $60.00 | $160.00 | $0.01 – $450.00 | Sep 30, 2026, line 0290 ↗ |
| 31” W-bm GR, Mid-way Splice- SGL Faced | linear foot | 271 | $34.00 | $40.00 | $10.00 – $365.00 | Sep 30, 2026, line 0190 ↗ |
| Seeding Method Number 1 | unit | 264 | $52.00 | $105.00 | $10.00 – $500.00 | Sep 23, 2026, line 0300 ↗ |
| Field Office Type A | each | 264 | $10,438 | $10,000 | $100.00 – $200,000 | Sep 30, 2026, line 0310 ↗ |
| 31” W-bm GR, Mid-way Splice Flared Terminal | each | 251 | $3,780 | $3,600 | $100.00 – $14,143 | Sep 16, 2026, line 0210 ↗ |