MaineDOT: awarded unit prices

55,310 winning bid prices read from 1,672 source documents, 2010–2026. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › MaineDOT

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Mobilizationls1,232—$290,000$0.01 – $9,059,000Sep 30, 2026, line 0390 ↗
Construction signsquare foot1,047$15.00$10.00$0.01 – $250.00Sep 30, 2026, line 0340 ↗
Coneeach1,034$20.00$20.00$0.01 – $421.04Sep 30, 2026, line 0330 ↗
Flaggerhour1,031$33.00$0.01$0.01 – $215.44Sep 30, 2026, line 0360 ↗
Temporary Soil Erosion and Water Pollution Controlls1,026—$50,000$0.01 – $1,250,000Sep 30, 2026, line 0380 ↗
Hand Labor, Straight Timehour956$45.00$50.00$0.01 – $256.00Sep 30, 2026, line 0270 ↗
Drumeach919$50.00$100.00$0.01 – $179.38Sep 30, 2026, line 0320 ↗
Truck - Large (Including Operator)hour906$90.00$140.00$0.01 – $500.00Sep 30, 2026, line 0300 ↗
All Purpose Excavator (Including Operator)hour900$150.00$235.00$0.01 – $500.00Sep 30, 2026, line 0280 ↗
Asphalt tack coat - appliedg895$10.00$10.00$1.00 – $223.00Sep 30, 2026, line 0070 ↗
Maintenance of Traffic Control Devicescd876—$1,000$0.01 – $1,950,000Sep 30, 2026, line 0350 ↗
4 inch white or yellow paint pavement marking linelinear foot718—$0.13$0.01 – $15.00Sep 30, 2026, line 0240 ↗
Mulchingunit667$42.65$40.00$1.00 – $5,000Sep 30, 2026, line 0230 ↗
Hot mix asphalt 9.5 mm (sidewalk, drives, incidentals)ton610$219.50$350.00$0.01 – $1,000Sep 30, 2026, line 0040 ↗
Common Excavationcubic yard552$24.00$45.00$0.01 – $500.00Sep 30, 2026, line 0030 ↗
Plain Riprapcubic yard541$83.00$68.25$1.00 – $594.50Sep 23, 2026, line 0270 ↗
Loamcubic yard538$62.00$160.00$1.00 – $1,000Sep 30, 2026, line 0260 ↗
Seeding Method Number 2unit529$45.00$1.00$1.00 – $3,000Sep 30, 2026, line 0220 ↗
Hot MIX Asphalt 12.5 MM Baseton522$195.00$200.00$66.50 – $800.00Sep 30, 2026, line 0060 ↗
Remove pavement surfacesquare yard515$12.00$38.00$0.01 – $500.00Sep 16, 2026, line 0010 ↗
Aggregate Subbase Course - Gravelcubic yard499$45.00$65.00$1.00 – $850.00Sep 30, 2026, line 0090 ↗
Pavement butt jointsquare yard493$14.28$30.00$0.01 – $100.00Sep 30, 2026, line 0020 ↗
Erosion Control Geotextilesquare yard492$4.00$4.25$1.00 – $100.00Sep 30, 2026, line 0310 ↗
Temporary 4 inch paint pavement marking line, white or yellowlinear foot482$0.15$0.13$0.01 – $12.00Sep 30, 2026, line 0260 ↗
Field Office Type Beach475$8,500$25,000$1.00 – $76,000Sep 30, 2026, line 0370 ↗
Erosion Control Blanketsquare yard475$4.00$4.00$0.74 – $55.00Sep 30, 2026, line 0250 ↗
Reflectorized Flexible Guardrail Markereach473$52.50$50.00$1.00 – $320.00Sep 30, 2026, line 0200 ↗
White or Yellow Pavement & Curb Markingsquare foot464$2.52$5.00$0.58 – $20.00Sep 30, 2026, line 0250 ↗
Portable Changeable Message Signeach458$3,600$3,000$1.00 – $33,900Sep 30, 2026, line 0370 ↗
Hot MIX Asphalt (Shimming)ton438$121.00$240.00$64.00 – $990.00Aug 5, 2026, line 0040 ↗
Granular Borrowcubic yard361$40.00$75.00$0.01 – $597.00Sep 30, 2026, line 0050 ↗
Type III Barricadeeach358$200.00$180.00$0.01 – $30,000Sep 30, 2026, line 0380 ↗
Curb Type 3linear foot319$24.00$25.00$4.90 – $300.00Jun 17, 2026, line 0110 ↗
Adjusting Manhole or Catch Basin to Gradeeach293$1,500$2,500$130.00 – $5,250Sep 30, 2026, line 0180 ↗
Hot mix asphalt 12.5 mm hot mix asphalt surfaceton290$190.00$245.00$64.84 – $1,000Sep 30, 2026, line 0100 ↗
Erosion Control MIXcubic yard283$60.00$160.00$0.01 – $450.00Sep 30, 2026, line 0290 ↗
31” W-bm GR, Mid-way Splice- SGL Facedlinear foot271$34.00$40.00$10.00 – $365.00Sep 30, 2026, line 0190 ↗
Seeding Method Number 1unit264$52.00$105.00$10.00 – $500.00Sep 23, 2026, line 0300 ↗
Field Office Type Aeach264$10,438$10,000$100.00 – $200,000Sep 30, 2026, line 0310 ↗
31” W-bm GR, Mid-way Splice Flared Terminaleach251$3,780$3,600$100.00 – $14,143Sep 16, 2026, line 0210 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.