KDOT: awarded unit prices

210,346 winning bid prices read from 5,912 source documents, 2007–2026. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › KDOT

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Mobilizationls5,829—$490,000$1.00 – $23,900,000Oct 21, 2026, line 3 ↗
Flagger (Set Price)hour5,556$25.00$30.00$1.00 – $70.00Oct 21, 2026, line 9 ↗
Traffic Controlls4,029—$18,000$1.00 – $786,957Oct 21, 2026, line 2 ↗
Field Office and Laboratory (Type A)each2,845$2,500$1,000$0.01 – $130,000Oct 21, 2026, line 71 ↗
Contractor Construction Stakingls2,204$6,750$35,000$1.00 – $2,300,000Oct 21, 2026, line 1 ↗
Remove of existing structurels2,191—$400,000$1.00 – $13,275,527Oct 21, 2026, line 4 ↗
Sediment remove (set price)cubic yard1,899$35.00$50.00$1.00 – $65.00Oct 21, 2026, line 31 ↗
Pavement marking removelinear foot1,888$0.49$0.15$0.01 – $15.00Oct 21, 2026, line 82 ↗
Pavement marking (multi-component) (white) (6 inch)linear foot1,848$0.55$0.71$0.25 – $50.00Oct 21, 2026, line 80 ↗
Reinforced steel (grade 60)pound1,845$1.09$1.50$0.4 – $95.00Oct 21, 2026, line 41 ↗
Maintenance and Restoration of Haul Roads (Set Price)ls1,810$4,000$4,000$3,500 – $16,000Oct 21, 2026, line 8 ↗
Water (Grading) (Set Price)thousand gallons1,802$35.00$40.00$8.00 – $65.00Oct 21, 2026, line 16 ↗
Clearing and Grubbingls1,795—$50,000$1.00 – $998,575Oct 21, 2026, line 10 ↗
Quality control testing (hot mix asphalt)ton1,734$1.25$1.60$0.01 – $17.23Oct 21, 2026, line 7 ↗
Traffic Control (Initial Setup)ls1,688$15,000$40,523$0.01 – $1,220,500Oct 21, 2026, line 92 ↗
Work zone sign (9.26 to 16.25 sq.ft.)eada1,616$0.25$0.16$0.01 – $7.00Oct 21, 2026, line 84 ↗
Work zone sign (0 to 9.25 sq.ft.)eada1,611$0.15$0.13$0.01 – $7.00Oct 21, 2026, line 83 ↗
Channelizer (Portable)eada1,596$0.1$0.13$0.001 – $2.00Oct 21, 2026, line 86 ↗
Hot mix asphalt-commercial grade (class a)ton1,579$110.00$170.00$2.50 – $2,460Oct 21, 2026, line 67 ↗
Pavement marking (multi-component) (yellow) (4 inch)linear foot1,558$0.4$0.54$0.23 – $50.00Oct 21, 2026, line 81 ↗
Rock Excavationcubic yard1,554$28.50$40.00$1.00 – $8,400Oct 21, 2026, line 13 ↗
Material for hot mix asphalt patch (set price)ton1,471$170.00$350.00$120.00 – $350.00Oct 21, 2026, line 10 ↗
Reinforced steel (grade 60) (epoxy coated)pound1,468$1.40$3.45$0.11 – $54.85Oct 21, 2026, line 50 ↗
Asphalt Core (Set Price)each1,401$45.00$50.00$1.00 – $170.00Oct 21, 2026, line 12 ↗
Millington1,332$13.47$31.90$1.65 – $525.26Oct 21, 2026, line 9 ↗
Work Zone Warning Light (Type"A" Low Intensity)eada1,325$0.25$0.05$0.01 – $5.00Oct 21, 2026, line 87 ↗
Temporary Surfacing Material (Aggregate) (Set Price)cubic yard1,314$35.00$50.00$25.00 – $150.00Oct 21, 2026, line 25 ↗
Foundation Stabilization (Set Price)cubic yard1,308$40.00$40.00$25.00 – $175.00Oct 21, 2026, line 5 ↗
Pavement Edge Wedge (Rock)ton1,303$36.00$51.00$6.15 – $2,500Oct 21, 2026, line 69 ↗
Concrete (Grade 4.0) (Ae)cubic yard1,300$653.26$3,600$5.50 – $17,640Oct 21, 2026, line 47 ↗
Temporary Berm (Set Price)linear foot1,227$1.00$2.00$1.00 – $50.00Oct 21, 2026, line 32 ↗
Water (Erosion Control) (Set Price)thousand gallons1,211$35.00$40.00$35.00 – $45.00Oct 21, 2026, line 39 ↗
Pavement marking (intersection grade) (white) (24 inch)linear foot1,192$15.15$20.00$2.00 – $68.00Oct 21, 2026, line 147 ↗
Emulsified Asphalt (SS-1HP)ton1,191$615.20$800.00$1.00 – $2,000Oct 21, 2026, line 8 ↗
Concrete for Seal Course (Set Price)cubic yard1,126$175.00$225.00$40.00 – $225.00Oct 21, 2026, line 6 ↗
Mobilization (Dbe)ls1,120—$18,000$1.00 – $640,000Sep 17, 2025, line 5 ↗
Millingsquare yard1,057—$11.00$0.26 – $108.00Oct 21, 2026, line 72 ↗
Asphalt air void pay adjustls1,047$1.00$1.00$1.00 – $1.25Dec 14, 2022, line 15 ↗
Common excavation (contractor furnish)cubic yard1,046$10.75$20.00$0.001 – $410.00Oct 21, 2026, line 12 ↗
Bridge Backwall Protection Systemsquare yard1,018$32.00$87.00$9.99 – $429.00Oct 21, 2026, line 62 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.