| Mobilization and Demobilization | ls | 6,005 | — | $172,000 | $1.00 – $28,229,229 | Sep 9, 2026, Sep 9, 2026 letting ↗ |
| Maintaining Traffic | ls | 5,530 | — | $150,000 | $1.00 – $12,504,485 | Sep 9, 2026, Sep 9, 2026 letting ↗ |
| Construction Engineering | ls | 5,146 | — | $1.00 | $1.00 – $6,268,626 | Sep 9, 2026, Sep 9, 2026 letting ↗ |
| Construction Sign, a | each | 4,328 | $125.00 | $190.00 | $0.5 – $1,606 | May 10, 2023, May 10, 2023 letting ↗ |
| Surface Seal | ls | 3,341 | $4,250 | $8,700 | $0.01 – $1,233,040 | Sep 9, 2026, Sep 9, 2026 letting ↗ |
| Mobilization and Demobilization for Seeding | each | 3,210 | $500.00 | $600.00 | $1.00 – $6,500 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Clearing Right of Way | ls | 3,164 | — | $149,000 | $1.00 – $5,700,000 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Road Closure Sign Assembly | each | 2,590 | $275.00 | $310.00 | $1.08 – $2,649 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Excavation, Common | cys | 2,403 | $45.00 | $63.00 | $0.01 – $1,800 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Detour Route Marker Assembly | each | 2,272 | $110.00 | $175.00 | $0.6 – $1,180 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Asphalt for Tack Coat | ton | 2,210 | $540.00 | $600.00 | $0.01 – $11,075 | Sep 9, 2026, Sep 9, 2026 letting ↗ |
| Computer System Equipment | each | 2,183 | $750.00 | $100.00 | $0.02 – $5,772 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Snowplowable Raised Pavement Marker, Remove | each | 2,171 | $11.00 | $13.50 | $0.01 – $1,650 | Sep 9, 2026, Sep 9, 2026 letting ↗ |
| Construction Sign, B | each | 2,033 | $70.00 | $99.00 | $0.1 – $520.00 | May 10, 2023, May 10, 2023 letting ↗ |
| Flashing Arrow Sign | day | 1,971 | $16.00 | $14.00 | $0.01 – $1,000 | Sep 9, 2026, Sep 9, 2026 letting ↗ |
| Stormwater Management Implementation | ls | 1,931 | $8,900 | $10,000 | $1.00 – $1,790,000 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Joint Adhesive, Surface | linear foot | 1,920 | $0.535 | $0.95 | $0.01 – $185.79 | Aug 6, 2025, Aug 6, 2025 letting ↗ |
| Snowplowable Raised Pavement Marker | each | 1,902 | $42.00 | $82.00 | $0.55 – $3,000 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Compaction aggregate no. 53 | ton | 1,862 | $47.71 | $58.00 | $1.00 – $940.00 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Riprap, Revetment | ton | 1,860 | $75.00 | $100.00 | $1.00 – $1,825 | Sep 9, 2026, Sep 9, 2026 letting ↗ |
| Liquid asphalt seal | linear foot | 1,823 | — | $0.25 | $0.01 – $54.00 | Feb 12, 2025, Feb 12, 2025 letting ↗ |
| Temporary Pavement Marking, Removable, 4 IN. | linear foot | 1,720 | $1.15 | $2.45 | $0.01 – $15.00 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Subgrade Treatment, Type IC | sys | 1,519 | $37.00 | $52.00 | $5.00 – $415.00 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Joint Adhesive, Intermediate | linear foot | 1,431 | $0.75 | $0.95 | $0.01 – $75.50 | Aug 6, 2025, Aug 6, 2025 letting ↗ |
| Guardrail End Treatment, Os | each | 1,377 | $2,925 | $3,280 | $1.00 – $8,572 | May 10, 2023, May 10, 2023 letting ↗ |
| Milling, Asphalt, 1 1/2 IN. | sys | 1,362 | — | $6.25 | $0.01 – $500.00 | Sep 9, 2026, Sep 9, 2026 letting ↗ |
| Geotextile FOR Riprap Type 1A | sys | 1,324 | $4.50 | $4.00 | $0.66 – $240.00 | Sep 9, 2026, Sep 9, 2026 letting ↗ |
| Guardrail, Remove | linear foot | 1,298 | $5.00 | $4.00 | $0.01 – $250.00 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Barricade, Iii-a | linear foot | 1,267 | $14.00 | $16.50 | $1.00 – $81.60 | May 10, 2023, May 10, 2023 letting ↗ |
| Line, Remove | linear foot | 1,259 | $0.65 | $0.51 | $0.01 – $13.95 | Sep 9, 2026, Sep 9, 2026 letting ↗ |
| Construction Sign, Type A | each | 1,252 | $201.34 | $189.00 | $1.00 – $1,125 | Sep 9, 2026, Sep 9, 2026 letting ↗ |
| Grooving for pavement marking | linear foot | 1,252 | $0.665 | $0.71 | $0.03 – $48.00 | Sep 9, 2026, Sep 9, 2026 letting ↗ |
| Compaction aggregate no. 53 | cys | 1,234 | $85.00 | $80.00 | $15.00 – $1,087 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Pavement remove | sys | 1,212 | $30.00 | $42.00 | $0.01 – $1,000 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Line, Paint, Solid, White, 4 IN. | linear foot | 1,170 | — | $0.55 | $0.04 – $29.00 | Aug 5, 2026, Aug 5, 2026 letting ↗ |
| Barricade, Iii-b | linear foot | 1,152 | $14.22 | $16.50 | $1.00 – $300.00 | May 10, 2023, May 10, 2023 letting ↗ |
| Sign, Sheet, With Legend, 0.080 IN. | square foot | 1,150 | $26.50 | $30.00 | $7.88 – $800.00 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Subgrade Treatment, Type II | sys | 1,148 | $25.00 | $100.00 | $3.00 – $735.00 | Sep 9, 2026, Sep 9, 2026 letting ↗ |
| Sodding | sys | 1,148 | — | $8.75 | $1.50 – $2,700 | Sep 2, 2026, Sep 2, 2026 letting ↗ |
| Right of Way Marker | each | 1,143 | $165.00 | $225.00 | $54.00 – $1,500 | Sep 2, 2026, Sep 2, 2026 letting ↗ |