| Overband Crack Fill, Lane | lnmi | 25 | $1,940 | $3,800 | $1,940 – $3,800 | Feb 20, 2026, Open bid tab, 26E200 ↗ |
| Pavement marking, waterborne, 4 inch, yellow | linear foot | 8 | $0.105 | $0.09 | $0.07 – $0.13 | Feb 20, 2026, Open bid tab, 26E200 ↗ |
| Pavement marking, waterborne, 4 inch, white | linear foot | 8 | $0.105 | $0.09 | $0.07 – $0.13 | Feb 20, 2026, Open bid tab, 26E200 ↗ |
| Hot mix asphalt, 36a wedge | ton | 7 | $72.75 | $70.50 | $70.00 – $78.00 | Mar 1, 2019, Open bid tab, 19E300 ↗ |
| Pavement marking, polyurea, 24 inch, stop bar | linear foot | 6 | $18.25 | $20.00 | $11.00 – $21.00 | Jul 29, 2026, Open bid tab, 25S302. ↗ |
| Ts, span wire mtd, remove | each | 5 | $300.00 | $150.00 | $150.00 – $350.00 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| Shoulder, class ii | ton | 5 | $32.00 | $36.00 | $22.00 – $36.00 | Mar 1, 2019, Open bid tab, 19E300 ↗ |
| Ts, one way span wire mtd, five section (led) | each | 4 | — | $2,750 | $2,150 – $2,780 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| TS, One Way Span Wire Mtd (LED) | each | 4 | — | $1,485 | $1,400 – $1,800 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| Pavement marking, polyurea, railroad symbol | each | 4 | — | $450.00 | $330.00 – $500.00 | Feb 20, 2026, Open bid tab, 26E200 ↗ |
| Hot mix asphalt, 5e1 | ton | 4 | — | $40.00 | $40.00 – $63.00 | Mar 1, 2019, Open bid tab, 19E300 ↗ |
| Cold milling hot mix asphalt surface | square yard | 4 | — | $5.00 | $5.00 | Mar 1, 2019, Open bid tab, 19E300 ↗ |
| TS, One Way Span Wire Mtd, FYA (LED) | each | 3 | — | $1,900 | $1,560 – $2,000 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| Case sign, remove | each | 3 | — | $150.00 | $150.00 – $350.00 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| Pavement marking, polyurea, only | each | 3 | — | $225.00 | $150.00 – $225.00 | Feb 20, 2026, Open bid tab, 26E200 ↗ |
| Hot mix asphalt, ultra-thin, medium volume | ton | 3 | — | $80.00 | $72.25 – $80.00 | Mar 1, 2019, Open bid tab, 19E300 ↗ |
| Pavement marking, polyurea, lt turn arrow symbol | each | 3 | — | $225.00 | $150.00 – $225.00 | Feb 20, 2026, Open bid tab, 26E200 ↗ |
| Hot mix asphalt, 4e1 | ton | 3 | — | $40.00 | $40.00 – $60.00 | Mar 1, 2019, Open bid tab, 19E300 ↗ |
| Mobilization, Max | ls | 3 | — | $9,000 | $9,000 – $67,985 | Sep 28, 2026, Open bid tab, 26TWA02 ↗ |
| Trench | station | 3 | — | $450.00 | $120.00 – $450.00 | Mar 1, 2019, Open bid tab, 19E300 ↗ |
| Hot mix asphalt base crushing and shaping | square yard | 3 | — | $7.20 | $1.35 – $7.20 | Mar 1, 2019, Open bid tab, 19E300 ↗ |
| Hot mix asphalt approach | ton | 3 | — | $40.00 | $40.00 – $80.00 | Mar 1, 2019, Open bid tab, 19E300 ↗ |
| Aggregate Base | ton | 3 | — | $15.50 | $11.00 – $15.50 | Mar 1, 2019, Open bid tab, 19E300 ↗ |
| Temporary Traffic Control | ls | 2 | — | $2,500 | $2,500 – $10,000 | Apr 16, 2026, Open bid tab, 26S201 ↗ |
| Mobilization, Max 5% | ls | 2 | — | $6,000 | $5,000 – $6,000 | Apr 16, 2026, Open bid tab, 26S201 ↗ |
| Ts, mast arm mtd, remove | each | 2 | — | $350.00 | $300.00 – $350.00 | Jul 29, 2026, Open bid tab, 25S302. ↗ |
| TS Uninterruptible Power System | each | 2 | — | $13,768 | $12,963 – $13,768 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| _ Street Name Sign, Two Way, 8 foot | each | 2 | — | $2,345 | $2,345 – $2,815 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| _ Street Name Sign, Two Way, 6 foot | each | 2 | — | $2,080 | $2,080 – $2,600 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| Hemispherical Video Detection System | each | 2 | — | $26,734 | $3,560 – $26,734 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| Hemispherical video detection camera, remove | each | 2 | — | $125.00 | $125.00 – $350.00 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| Hemispherical Video Detection Camera | each | 2 | — | $10,950 | $10,950 – $11,200 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| Cabinet, Nema Type | each | 2 | — | $18,355 | $18,355 – $19,650 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| Casing, 48 Inch | linear foot | 2 | — | $490.00 | $490.00 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| Bracket, Truss, with 18 Foot Arm | each | 2 | — | $2,005 | $2,005 – $2,500 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| Span wire, remove | each | 2 | — | $120.00 | $120.00 – $350.00 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| Controller fdn, remove | each | 2 | — | $400.00 | $400.00 – $1,000 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| Controller Fdn, Base Mtd | each | 2 | — | $3,600 | $3,600 – $4,285 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| Controller and cabinet, remove | each | 2 | — | $150.00 | $150.00 – $350.00 | Jul 29, 2026, Open bid tab, 23S301 ↗ |
| _ TS, Service Rack, Metered | each | 2 | — | $1,875 | $1,875 | Jul 29, 2026, Open bid tab, 23S301 ↗ |