| Materials testing service | allow | 1 | — | $25,000 | $25,000 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Municipal Permit Fees | allow | 1 | — | $2,500 | $2,500 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Information Technology Equipment | allow | 1 | — | $15,000 | $15,000 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Utility Service and Relocation Charges | allow | 1 | — | $75,000 | $75,000 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Disposal of Hazardous or Contaminated Materials, Including Asbestos Pipe | allow | 1 | — | $55,000 | $55,000 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Contaminated Soil Excavation Offsite Disposal Fees | allow | 1 | — | $50,000 | $50,000 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| 1.5-inch milling and final pavement, additional | square yard | 1 | — | $1.00 | $1.00 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Asphalt concrete paving, additional | ton | 1 | — | $1.00 | $1.00 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Screened Stone, Additional | cubic yard | 1 | — | $1.00 | $1.00 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Gravel Borrow/Select Fill, Additional | cubic yard | 1 | — | $1.00 | $1.00 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Processed Gravel, Additional | cubic yard | 1 | — | $1.00 | $1.00 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Ordinary/Common Borrow, Additional | cubic yard | 1 | — | $1.00 | $1.00 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Backfill with Flowable Fill, Additional | cubic yard | 1 | — | $1.00 | $1.00 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Earthwork Excavation and Disposal, Additional | cubic yard | 1 | — | $1.00 | $1.00 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Trench Excavation - Ledge | cubic yard | 1 | — | $1.00 | $1.00 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Pvc sewer pipe, all sizes up to 12 inch | linear foot | 1 | — | $220.00 | $220.00 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Water Booster Pump Station Control System Programming | allow | 1 | — | $25,000 | $25,000 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Sewer Pump Station Control System Programming | allow | 1 | — | $25,000 | $25,000 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Variable Frequency Drives | allow | 1 | — | $70,000 | $70,000 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Standby Generator | allow | 1 | — | $90,000 | $90,000 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Water Booster Pump Equipment Skid | allow | 1 | — | $70,000 | $70,000 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Submersible Sewage Pump Equipment | allow | 1 | — | $70,000 | $70,000 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Booster Pump Station, Excluding Unit rice Items | ls | 1 | — | $3,900,000 | $3,900,000 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Price Adjustments | allow | 1 | — | $25,000 | $25,000 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Concrete, additional | cubic yard | 1 | — | $1.00 | $1.00 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Test Pit | each | 1 | — | $1.00 | $1.00 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |
| Sewer Manhole | each | 1 | — | $10,000 | $10,000 | May 13, 2022, Open bid tab, 14257_20382-WilsonRd-Bid-Tabulation.pdf ↗ |