| Septage Receiving Upgrade | ls | 1 | — | $165,000 | $165,000 | Jul 22, 2024, Open bid tab, Septage Receiving Upgrade/21338 ↗ |
| Sole Source VTSCADA Runtime License Allowance | allow | 1 | — | $5,000 | $5,000 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Sole Source Foxvoro Flow Meter | allow | 1 | — | $5,000 | $5,000 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Sole Source Allen-Bradley PLC | allow | 1 | — | $4,500 | $4,500 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Utility Service Allowance | allow | 1 | — | $15,000 | $15,000 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Asbestos cement pipe remove and disposal | linear foot | 1 | — | $75.00 | $75.00 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Asphalt sidewalk/walkway | ton | 1 | — | $300.00 | $300.00 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Driveway Pavement | ton | 1 | — | $300.00 | $300.00 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Final Trench Pavement | ton | 1 | — | $150.00 | $150.00 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Initial Trench Pavement | ton | 1 | — | $150.00 | $150.00 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| 4-inch Sewer | linear foot | 1 | — | $175.00 | $175.00 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| 12-inch Sewer | linear foot | 1 | — | $400.00 | $400.00 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| 4-foot Diameter Sewer Manhole (SMH-295 and SMH-3) | vf | 1 | — | $1,000 | $1,000 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| 12-inch HDPE Force Main Pipe | linear foot | 1 | — | $150.00 | $150.00 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Webster Avenue Pump Station | ls | 1 | — | $3,725,000 | $3,725,000 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Replace of unsuitable material above pipe bedding and initial backfill | cubic yard | 1 | — | $75.00 | $75.00 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Loam and Seed | ls | 1 | — | $15,000 | $15,000 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Pipe Trench Insulation | linear foot | 1 | — | $20.00 | $20.00 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Ledge Excavation | cubic yard | 1 | — | $400.00 | $400.00 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Excavation below grade and replace backfill | cubic yard | 1 | — | $75.00 | $75.00 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Test Pit Excavation and Backfill | each | 1 | — | $1.00 | $1.00 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Erosion and sediment control | ls | 1 | — | $15,000 | $15,000 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Asphalt curb | linear foot | 1 | — | $250.00 | $250.00 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Traffic Control | ls | 1 | — | $35,000 | $35,000 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Pre-Blast Survey | each | 1 | — | $1.00 | $1.00 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |
| Mobilization and Demobilization | ls | 1 | — | $150,000 | $150,000 | Jan 8, 2024, Open bid tab, Webster Avenue Pump Station and Force Main Upgrade/ 21244B ↗ |