Erie County Water Authority: awarded unit prices

169 winning bid prices read from 8 source documents, 2025–2026. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › Erie County Water Authority

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
20A Excavation to Determine Service Material in Asphalt/Concrete Areaseach5$421.00$420.00$339.40 – $540.00Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
19A Vacuum Excavation to Determine Service Material in Lawn Areaeach5$390.00$390.00$337.68 – $500.00Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
16A Contingency Allowancels5$300,000$300,000$50,000 – $350,000Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
11b4 furnish and install asphalt pavement - binder course (2.5 inch deep)square yard5$23.90$22.00$22.00 – $81.00Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
11b3 furnish and install asphalt pavement - top course (1.5 inch deep)square yard5$21.00$18.00$18.00 – $81.00Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
11B2 Furnish and Install Asphalt Driveway/Parking Lotsquare yard5$57.63$36.00$36.00 – $95.00Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
11A2 Furnish and Install Concrete Drivewaysquare yard5$120.00$85.00$85.00 – $195.00Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
11A1 Furnish and Install Concrete Sidewalksquare yard5$120.00$75.00$75.00 – $235.00Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
11b5 furnish and install asphalt pavement - base course (4 inch deep)square yard4—$29.00$29.00 – $110.00Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
21A New Penetration of Foundation Wall or Flooreach3—$700.00$500.00 – $700.00Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
14A Repair Crew Labor and Equipmenthour3—$290.00$290.00 – $528.40Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
11C1 Landscape Restorationsquare yard3—$23.00$20.00 – $24.88Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
11b6 cold milling and placement of asphalt pavement (1.5 inch deep)square yard3—$19.00$17.18 – $19.00Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
8B4 Furnish and Install 1 1/2-inch and Larger Copper Tubing (Private Side)linear foot3—$13.00$11.00 – $27.26Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
8B3 Furnish and Install 3/4-inch to 1-inch Copper Tubing (Private Side)linear foot3—$12.00$8.40 – $12.00Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
8B2 Furnish and Install 1 1/2-inch and Larger Copper Tubing (Public Side)linear foot3—$13.00$11.00 – $27.26Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
8B1 Furnish and Install 3/4-inch to 1-inch Copper Tubing (Public Side)linear foot3—$12.00$8.40 – $12.00Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
8a4 service replace/install 1 1/2-inch and larger (private side)each3—$3,900$3,900 – $7,572Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
8a3 service replace/install 3/4-inch to 1-inch (private side)each3—$3,600$3,600 – $6,355Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
8a2 service replace/install 1 1/2-inch and larger (public side)each3—$3,700$3,000 – $6,724Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
8a1 service replace/install 3/4-inch to 1-inch (public side)each3—$3,500$3,457 – $3,575Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
6A Furnish and Install Select Backfillcubic yard3—$49.00$49.00 – $70.00Feb 10, 2026, Open bid tab, contract 2026-02-10_bid_tabulation ↗
5a asphalt sealsquare yard2—$4.00$0.5 – $4.00Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
4A-2 Material Allowancels2—$25,000$25,000Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
4A-1 Crew and Equipmenthour2—$600.00$100.00 – $600.00Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
3i for fibers for concrete reinforcedcubic yard2—$10.00$5.50 – $10.00Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
3h inductance loop installlinear foot2—$33.00$33.00 – $40.00Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
3G Crushed Stonecubic yard2—$70.00$36.00 – $70.00Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
3f reinforced deformed steel barspound2—$2.00$0.25 – $2.00Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
3E Welded Wire Fabricsquare yard2—$2.50$2.50 – $7.00Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
3D Integral Curblinear foot2—$75.00$59.00 – $75.00Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
3C Gutter Curbcubic yard2—$1,100$500.00 – $1,100Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
3b sidewalk of 4 inch thick and driveway of 6 inch thickcubic yard2—$1,100$1,100 – $1,460Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
3a pavement of 8-inch thickcubic yard2—$900.00$100.00 – $900.00Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
2L Rough Dirt Fillcubic yard2—$30.00$9.00 – $30.00Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
2k additional spoil materials removecubic yard2—$50.00$30.00 – $50.00Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
2j fertilizing existing treeeach2—$170.00$22.00 – $170.00Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
2i replace evergreen shrub 2.5 feet to 4 feet tall(balled)each2—$475.00$45.00 – $475.00Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
2h replace deciduous shrub 3 feet - 4 feet tall (bare root)each2—$450.00$45.00 – $450.00Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗
2g repairing damaged tree, pruning, and wrappingeach2—$175.00$25.00 – $175.00Feb 19, 2026, Open bid tab, contract 2026-02-19_bid_tabulation ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.