CTDOT: awarded unit prices

88,268 winning bid prices read from 957 source documents, 2013–2026. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › CTDOT

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Maintenance and Protection of Traffic ** See Special Provisions **ls850—$65,000$500.00 – $11,000,000Oct 28, 2026, line 1090 ↗
Traffic Drumeach730$83.00$100.00$0.01 – $1,000Oct 7, 2026, line 1120 ↗
Mobilization and Project Closeoutls683—$190,000$2,500 – $35,000,000Oct 28, 2026, line 1110 ↗
Barricade Warning Lights - High Intensityday603$1.00$1.00$0.01 – $1,500Oct 28, 2026, line 1120 ↗
Cut asphalt concrete pavementlinear foot571$4.00$3.00$0.1 – $50.00Oct 7, 2026, line 0100 ↗
Construction signsquare foot553$20.00$50.00$0.01 – $100.00Oct 28, 2026, line 1160 ↗
Earth Excavationcubic yard552$30.00$25.00$1.00 – $800.00Oct 28, 2026, line 0070 ↗
Construction Field Office, Medium ** See Special Provisions **month539$3,500$4,000$100.00 – $28,000Oct 28, 2026, line 1060 ↗
Trafficperson (Uniformed Flagger)hour513$60.00$50.00$0.01 – $625.00Oct 28, 2026, line 1080 ↗
Furnishing and Placing Topsoilsquare yard513$10.00$15.00$1.00 – $350.00Oct 28, 2026, line 0650 ↗
Material for Tack Coatgallon497$10.00$8.35$0.01 – $164.00May 6, 2026, line 0200 ↗
42'' Traffic Coneeach485$43.00$47.37$0.01 – $151.00Aug 26, 2026, line 0360 ↗
Clearing and Grubbingls482—$125,000$250.00 – $9,060,000Oct 28, 2026, line 0060 ↗
Formation of Subgradesquare yard479$5.00$7.50$0.1 – $140.00Oct 28, 2026, line 0180 ↗
Trafficperson (Municipal Police Officer) (Estimated Cost)est.473$1.00$1.00$1.00 – $60,000Oct 28, 2026, line 1070 ↗
Sediment control systemlinear foot473$6.00$5.00$1.00 – $91.00Oct 28, 2026, line 0240 ↗
Remove of pavement markingsquare foot469$1.50$0.53$0.01 – $25.00Oct 7, 2026, line 1270 ↗
Hot mix asphalt s0.5ton464$153.25$200.00$77.00 – $2,400Oct 7, 2026, line 0220 ↗
Remove and relocation of existing sign ** see special provisions **ls414—$350.00$100.00 – $257,056Oct 7, 2026, line 1180 ↗
Asphalt adjust cost (estimated cost) ** see special provisions **est.397$1.00$1.00$1.00 – $20,000Oct 28, 2026, line 0290 ↗
Hot-applied paint pavement marking 4'' whitelinear foot391$0.25$1.58$0.12 – $7.50Oct 7, 2026, line 1210 ↗
Hot-applied paint pavement marking 4'' yellowlinear foot390$0.25$1.00$0.12 – $7.50Sep 23, 2026, line 1100 ↗
Construction Barricade Type IIIeach374$143.38$125.00$0.01 – $600.00Oct 28, 2026, line 1140 ↗
4 inch yellow epoxy resin pavement markinglinear foot372$0.68$25.00$0.28 – $25.00Sep 30, 2026, line 0720 ↗
4 inch white epoxy resin pavement markinglinear foot360$0.66$25.00$0.36 – $25.00Sep 30, 2026, line 0710 ↗
Subbasecubic yard360$50.00$85.00$10.00 – $6,090Oct 7, 2026, line 0150 ↗
Processed Aggregate Basecubic yard352$60.00$75.00$18.70 – $1,353Oct 28, 2026, line 0260 ↗
Epoxy resin pavement marking, symbols and legendssquare foot350$5.30$9.98$3.00 – $45.00Oct 7, 2026, line 1240 ↗
Traffic Coneeach347$20.00$20.00$0.01 – $109.00Oct 28, 2026, line 1130 ↗
Granular Fillcubic yard343$68.00$85.00$1.00 – $750.00Oct 28, 2026, line 0220 ↗
Remove Metal Beam Raillinear foot318$5.50$2.10$1.00 – $180.00Oct 7, 2026, line 0840 ↗
Asphalt concrete lip curbinglinear foot313$11.00$32.00$4.00 – $200.00Sep 23, 2026, line 0240 ↗
Repair Guiderail (Estimated Cost) ** See Special Provisions **est.313$1.00$1.00$1.00 – $500.00Oct 7, 2026, line 0850 ↗
Hot mix asphalt s1ton303$148.68$245.00$71.50 – $4,000Oct 7, 2026, line 0210 ↗
Construction Surveyingls302$33,000$50,000$1,000 – $6,000,000Oct 28, 2026, line 1150 ↗
Sign Face - Sheet Aluminum (Type IX Retroreflective Sheeting) ** See Special Provisions **square foot290$70.00$100.00$26.00 – $881.00Oct 7, 2026, line 1190 ↗
Hot-applied paint legend, arrows and markingsquare foot289$1.35$4.73$0.65 – $15.00Oct 7, 2026, line 1230 ↗
Remote Control Changeable Message Signday284$50.00$40.00$0.01 – $1,400Sep 2, 2026, line 0820 ↗
Concrete Sidewalksquare foot282$18.00$14.00$7.00 – $250.00Sep 23, 2026, line 0800 ↗
Temporary Precast Concrete Barrier Curblinear foot268$40.00$75.00$1.00 – $125.00Feb 2, 2022, line 0880 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.

More prices in Connecticut: statewide figures.