Burlington, MA: awarded unit prices

122 winning bid prices read from 2 source documents, 2021–2025. The table lists the 40 items this agency awarded most often. Winning bids only; every row links to a bid tabulation.

Cost by state › Agencies › Burlington, MA

ItemPerWinning bidsMedianLatest awardLowest – highestLatest source document
Loam & Seedsquare yard2—$50.00$30.00 – $50.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Remove and Reset Existing Guardraillinear foot2—$100.00$50.00 – $100.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Price adjust diesel fuelallow2—$15,000$15,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Excavation below grade and replace backfillcubic yard2—$1.00$0.01 – $1.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Vacuum Excavation Test Pitseach2—$3,000$3,000 – $5,100Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
1-inch Manual Air Release Valveeach2—$6,000$4,000 – $6,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Remove and Stack Existing Hydrantseach2—$200.00$0.01 – $200.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
10 inch gate valveeach2—$4,000$2,800 – $4,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Price adjust hot mix asphaltallow2—$10,000$2,500 – $10,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Price adjust gasoline fuelallow2—$5,000$2,500 – $5,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Mechanical Sweepingday2—$100.00$0.01 – $100.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
10 inch di water mainlinear foot2—$400.00$150.00 – $400.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
1 Inch Copper Service Pipelinear foot2—$150.00$100.00 – $150.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
4 inch di water mainlinear foot2—$300.00$150.00 – $300.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
1 inch corporation stopseach2—$6,000$1,200 – $6,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
16 inch butterfly valveeach2—$20,000$5,800 – $20,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
12 inch di water mainlinear foot2—$400.00$200.00 – $400.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
8 inch di water mainlinear foot2—$400.00$150.00 – $400.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
6 inch di water mainlinear foot2—$300.00$150.00 – $300.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
12 inch gate valveeach2—$5,000$2,900 – $5,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
6 inch gate valveeach2—$2,000$1,300 – $2,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
8 inch gate valveeach2—$3,000$1,700 – $3,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
16 inch di water mainlinear foot2—$500.00$250.00 – $500.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
24 inch di water mainlinear foot2—$570.00$350.00 – $570.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
24 inch butterfly valveeach2—$40,000$12,000 – $40,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Utility Coordinationls2—$5,000$5,000 – $25,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Traffic Controlls2—$100,000$52,000 – $100,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Construction of Flow Control Vault and Venturi Flow Meter Vault, including site work, electrical/controls, and associated piping and appurtenancesls1—$400,000$400,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Replace of butterfly valve at 121 middlesex turnpikels1—$50,000$50,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Remove and disposal of concrete roadway subbasecubic yard1—$600.00$600.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Remove and disposal of asbestos cement pipelinear foot1—$100.00$100.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Engineers Temporary Field Trailermonth1—$6,000$6,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Traffic Control Loop Detector Restorationls1—$30,000$30,000Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Remove and Reset and/or Replace Fencelinear foot1—$100.00$100.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Remove and Reset Existing Granite Curbslinear foot1—$70.00$70.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Portland cement concrete sidewalk, walkways, and driveway apronssquare yard1—$100.00$100.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Asphalt sidewalkton1—$200.00$200.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Weekly Pavementton1—$200.00$200.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Daily Pavementton1—$200.00$200.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗
Aggregate subbase, base and drivewaycubic yard1—$10.00$10.00Apr 30, 2025, Open bid tab, Phase 2B - 24" Water Main Replacement Project - MWRA Connection / 21894 ↗

These are prices this agency awarded, not quotes, and are not adjusted for quantity, location or timing. A median appears from 5 winning bids when the prices are consistent; otherwise the row shows the latest award and the range.