| Erosion Control, Silt Fence | linear foot | 56 | $2.00 | $3.00 | $0.9 – $16.00 | Oct 28, 2026, Open bid tab, LH 400322 ↗ |
| Sign, type b, temporary, modified | square foot | 50 | $7.50 | $8.00 | $2.00 – $15.00 | Jun 11, 2025, Open bid tab, lh400254-19thstreet ↗ |
| Station Grading | ls | 48 | $63,345 | $144,000 | $1,500 – $240,000 | Feb 19, 2025, Open bid tab, lh400246120thave ↗ |
| Subbase, CIP | cubic yard | 47 | $7.10 | $9.75 | $0.01 – $15.00 | Jun 11, 2025, Open bid tab, lh400254-19thstreet ↗ |
| Traffic Control | ls | 47 | $5,500 | $12,000 | $1,500 – $24,235 | Apr 23, 2026, Open bid tab, LH 400332 ↗ |
| _ shoulder preparation | ls | 47 | $3,500 | $5,500 | $1.00 – $20,000 | Apr 23, 2026, Open bid tab, LH 400332 ↗ |
| Extended Restoration | ls | 47 | $1,000 | $1,000 | $0.01 – $6,000 | Oct 28, 2026, Open bid tab, LH 400322 ↗ |
| Pavement for butt joint, remove | square yard | 46 | $7.00 | $8.00 | $4.00 – $38.13 | Apr 23, 2026, Open bid tab, LH 400332 ↗ |
| Approach, class ii | ton | 46 | $17.00 | $200.00 | $5.00 – $200.00 | Oct 28, 2026, Open bid tab, LH 400322 ↗ |
| _ approach, class ii, driveway | each | 45 | $110.00 | $120.00 | $100.00 – $250.00 | Apr 23, 2026, Open bid tab, LH 400332 ↗ |
| Subgrade Undercutting, Type II | cubic yard | 44 | — | $0.01 | $0.01 – $20.00 | Jun 11, 2025, Open bid tab, lh400254-19thstreet ↗ |
| Project Cleanup | ls | 44 | $1,688 | $1.00 | $1.00 – $32,000 | Jun 11, 2025, Open bid tab, lh400254-19thstreet ↗ |
| Clearing | ls | 44 | $48,625 | $100,000 | $500.00 – $150,000 | Feb 19, 2025, Open bid tab, lh400246120thave ↗ |
| Riprap, Plain | square yard | 43 | $50.00 | $70.00 | $0.01 – $110.00 | Apr 9, 2025, Open bid tab, lh400236130thave ↗ |
| Aggregate Base, 6 Inch | square yard | 43 | $4.60 | $5.25 | $2.30 – $8.83 | Jun 11, 2025, Open bid tab, lh400254-19thstreet ↗ |
| Geotextile, Stabilization | square yard | 42 | $2.00 | $2.95 | $0.01 – $10.00 | Jun 11, 2025, Open bid tab, lh400254-19thstreet ↗ |
| Culvert, class f, 12 inch | linear foot | 41 | $16.00 | $30.00 | $9.00 – $34.00 | Apr 15, 2026, Open bid tab, LH 400194 ↗ |
| Topsoil Surface, Salv, LM | cubic yard | 40 | $5.00 | $4.00 | $1.00 – $12.00 | May 8, 2024, Open bid tab, lh400141-28thst ↗ |
| Culvert, class f, 18 inch | linear foot | 39 | $22.00 | $40.00 | $14.00 – $44.00 | Apr 15, 2026, Open bid tab, LH 400194 ↗ |
| Underdrain, Subgrade, 6 Inch | linear foot | 38 | $4.00 | $6.00 | $0.01 – $7.00 | Apr 8, 2026, Open bid tab, LH 400191 ↗ |
| Plastic Drum, High Intensity, Lighted, Modified | each | 37 | $22.90 | $24.00 | $12.00 – $45.00 | Apr 8, 2026, Open bid tab, LH 400191 ↗ |
| Underdrain, Outlet Ending, 6 Inch | each | 36 | $150.00 | $250.00 | $0.01 – $280.00 | Apr 8, 2026, Open bid tab, LH 400191 ↗ |
| Underdrain Outlet, 6 Inch | linear foot | 36 | $10.50 | $15.00 | $0.01 – $24.00 | Apr 8, 2026, Open bid tab, LH 400191 ↗ |
| Monument box adjust | each | 36 | $150.00 | $150.00 | $100.00 – $250.00 | Apr 23, 2026, Open bid tab, LH 400332 ↗ |
| Pavement marking, waterborne, 4 inch, yellow | linear foot | 36 | $0.1 | $0.33 | $0.08 – $1.00 | Apr 23, 2026, Open bid tab, LH 400332 ↗ |
| Culvert end section, concrete, 18 inch | each | 36 | $662.50 | $900.00 | $450.00 – $1,300 | Apr 15, 2026, Open bid tab, LH 400194 ↗ |
| _ pavement marking, type nr, tape, 4-inch, yellow, temporary | station | 34 | $4.00 | $4.00 | $2.00 – $10.00 | Apr 23, 2026, Open bid tab, LH 400332 ↗ |
| Barricade Type III, High Intensity, Dbl Sided, Ltd, Modified | each | 34 | $177.50 | $250.00 | $75.00 – $300.00 | Oct 28, 2026, Open bid tab, LH 400322 ↗ |
| Pavement marking, waterborne, 4 inch, white | linear foot | 34 | $0.1 | $0.15 | $0.07 – $0.5 | Apr 23, 2026, Open bid tab, LH 400332 ↗ |
| Hot mix asphalt, 4el | ton | 34 | $71.83 | $170.00 | $64.37 – $250.00 | Oct 28, 2026, Open bid tab, LH 400322 ↗ |
| Aggregate, 6A | ton | 33 | $22.00 | $45.00 | $0.01 – $63.00 | Apr 8, 2026, Open bid tab, LH 400191 ↗ |
| Culvert, class e, concrete, 18 inch | linear foot | 33 | $48.00 | $120.00 | $19.00 – $120.00 | Apr 15, 2026, Open bid tab, LH 400194 ↗ |
| Erosion Control, Check Dam | linear foot | 31 | $15.00 | $5.00 | $0.01 – $45.00 | Jun 11, 2025, Open bid tab, lh400254-19thstreet ↗ |
| _ shoulder, class ii, modified | square yard | 31 | $5.50 | $6.50 | $3.00 – $6.50 | Apr 23, 2026, Open bid tab, LH 400332 ↗ |
| _ mailbox post, modified | each | 28 | $50.00 | $75.00 | $0.01 – $125.00 | Apr 23, 2026, Open bid tab, LH 400332 ↗ |
| Restoration | ls | 27 | $6,000 | $4,500 | $1,500 – $30,000 | Jun 3, 2020, Open bid tab, lh4021bidtab2 ↗ |
| _ pavement remove, modified | square yard | 27 | — | $1.00 | $0.01 – $100.00 | Apr 23, 2026, Open bid tab, LH 400338 ↗ |
| Mulching blanket, high velocity | square yard | 25 | $1.50 | $2.00 | $0.9 – $3.00 | Jun 3, 2020, Open bid tab, lh4021bidtab2 ↗ |
| Slope Restoration, Type C | square yard | 25 | $2.75 | $3.00 | $1.60 – $5.00 | Jun 11, 2025, Open bid tab, lh400254-19thstreet ↗ |
| Approach, hot mix asphalt millings | ton | 25 | $26.00 | $50.00 | $20.00 – $50.00 | Apr 15, 2026, Open bid tab, LH 400194 ↗ |