| Construction Surveying | ls | 267 | $20,000 | $30,000 | $600.00 – $95,000 | Aug 1, 2018, Open bid tab, 47167 ↗ |
| Standard Sign | square foot | 262 | $100.00 | $200.00 | $18.00 – $400.00 | Aug 1, 2018, Open bid tab, 47167 ↗ |
| Field Office | ls | 238 | $18,458 | $15,000 | $2.20 – $80,000 | Aug 1, 2018, Open bid tab, 47167 ↗ |
| CPM Scheduling | ls | 231 | $2,000 | $600.00 | $0.01 – $55,000 | Jul 1, 2018, Open bid tab, 48449 ↗ |
| Aggregate Base Course, Grading D-1 | ton | 213 | $28.30 | $32.00 | $0.01 – $300.00 | Jul 1, 2018, Open bid tab, 48449 ↗ |
| Three Person Survey Party | hour | 187 | $300.00 | $450.00 | $0.01 – $540.50 | Aug 1, 2018, Open bid tab, 47167 ↗ |
| Traffic Maintenance | ls | 170 | $17,830 | $20,000 | $0.52 – $90,000 | Aug 1, 2018, Open bid tab, 47167 ↗ |
| Permanent construction sign | ls | 158 | $13,550 | $1.00 | $1.00 – $85,000 | Jun 1, 2018, Open bid tab, 48417 ↗ |
| Unclassified Excavation | cubic yard | 152 | $11.75 | $12.00 | $2.00 – $160.72 | Aug 1, 2018, Open bid tab, 47167 ↗ |
| Seeding | pound | 145 | $80.00 | $195.00 | $10.00 – $2,000 | Jul 1, 2018, Open bid tab, 48449 ↗ |
| SWPPP Manager | ls | 143 | — | $3,500 | $0.01 – $95,000 | Jul 1, 2018, Open bid tab, 48449 ↗ |
| W-beam Guardrail | linear foot | 141 | $33.00 | $25.00 | $12.70 – $175.00 | Jun 1, 2018, Open bid tab, 48393 ↗ |
| Vehicles | ls | 137 | $20,000 | $5,500 | $2.40 – $73,000 | Jun 1, 2018, Open bid tab, 48004 ↗ |
| Approach | each | 128 | $1,000 | $900.00 | $100.00 – $11,500 | Jul 1, 2018, Open bid tab, 48468 ↗ |
| Flagging | contingent sum | 115 | $25,000 | $10,440 | $2,000 – $98,400 | Jul 1, 2018, Open bid tab, 48449 ↗ |
| Traffic Control | contingent sum | 113 | $30,000 | $10,000 | $1,000 – $99,000 | Jul 1, 2018, Open bid tab, 48449 ↗ |
| Paint traffic marking | ls | 110 | $15,000 | $1,650 | $500.00 – $68,000 | Jul 1, 2018, Open bid tab, 48449 ↗ |
| Remove of pavement | square yard | 107 | $5.00 | $6.25 | $0.01 – $115.00 | Jul 1, 2018, Open bid tab, 48265 ↗ |
| Remove and disposing of guardrail | linear foot | 107 | $5.00 | $2.00 | $1.00 – $100.00 | Jun 1, 2018, Open bid tab, 48393 ↗ |
| STE-1 Asphalt For Tack Coat | ton | 106 | $1,000 | $1.00 | $0.01 – $40,000 | Jul 1, 2018, Open bid tab, 48468 ↗ |
| Curb Ramp | each | 106 | $2,075 | $775.00 | $707.00 – $5,700 | Jul 1, 2018, Open bid tab, 48265 ↗ |
| Worker Meals and Lodging, or Per Diem | ls | 101 | $13,000 | $15,000 | $1.00 – $90,000 | Jun 1, 2018, Open bid tab, 48004 ↗ |
| Erosion, Sediment and Pollution Control Administration | ls | 96 | $8,750 | $6,000 | $500.00 – $74,800 | Jul 1, 2018, Open bid tab, 48449 ↗ |
| Erosion, Sediment and Pollution Control | ls | 95 | $9,000 | $12,000 | $2.00 – $39,000 | Jun 1, 2018, Open bid tab, 48367 ↗ |
| Mobilization and Demobilization | ls | 88 | $20,000 | $20,000 | $500.00 – $96,260 | Jul 1, 2018, Open bid tab, 48449 ↗ |
| Adjust Existing Manhole | each | 88 | $935.50 | $1,704 | $200.00 – $4,592 | Jun 1, 2018, Open bid tab, 48417 ↗ |
| Topsoil | square yard | 87 | $4.00 | $5.50 | $0.15 – $47.00 | Jul 1, 2018, Open bid tab, 48449 ↗ |
| Atb | ton | 86 | $93.75 | $73.00 | $27.00 – $242.55 | Jul 1, 2018, Open bid tab, 48468 ↗ |
| Engineering Communications | contingent sum | 85 | $5,000 | $10,000 | $500.00 – $75,000 | Aug 1, 2018, Open bid tab, 47167 ↗ |
| Parallel Guardrail Terminal | each | 82 | $4,000 | $3,418 | $1,800 – $13,000 | Jun 1, 2018, Open bid tab, 48417 ↗ |
| Field Laboratory | ls | 80 | $15,000 | $15,000 | $1.00 – $45,000 | Jun 1, 2018, Open bid tab, 47740 ↗ |
| Remove of culvert pipe | linear foot | 79 | $20.00 | $9.00 | $4.10 – $200.00 | Jul 1, 2018, Open bid tab, 48265 ↗ |
| Culvert Marker Post | each | 78 | $150.00 | $200.00 | $67.00 – $1,100 | Jul 1, 2018, Open bid tab, 48451 ↗ |
| Salvage Sign | each | 73 | $100.00 | $53.40 | $25.00 – $800.00 | Jun 1, 2018, Open bid tab, 48417 ↗ |
| Three Person Survey Party | contingent sum | 70 | $17,000 | $10,000 | $2,000 – $60,000 | Jun 1, 2018, Open bid tab, 48004 ↗ |
| Asphalt Cement, Grade PG 52-28 | ton | 68 | — | $0.01 | $0.01 – $1,350 | Aug 1, 2016, Open bid tab, 46181 ↗ |
| Hot Mix Asphalt, Type II; Class A | ton | 67 | $110.00 | $173.00 | $40.00 – $490.00 | Aug 1, 2018, Open bid tab, 48503 ↗ |
| Curb and Gutter, Type 1 | linear foot | 66 | $36.50 | $82.00 | $14.10 – $135.45 | Jul 1, 2018, Open bid tab, 48265 ↗ |
| Seeding | acre | 64 | $5,000 | $5,000 | $1,215 – $31,820 | Aug 1, 2018, Open bid tab, 47167 ↗ |
| Asphalt Concrete, Type II; Class B | ton | 64 | $96.00 | $72.00 | $30.50 – $2,575 | Sep 1, 2015, Open bid tab, 45127 ↗ |