Remov & RE - Lay Pipe (42 in)
Median winning unit price
Thin 3 winning bids≈$131/ LFLow confidence
- Winning bids
- 3
- Source documents
- 3
Winning bids only, as awarded. Nominal dollars. How we compute this
Where the number comes from
One of the 3 winning bids behind that median, with the agency’s own document one click away.
- Agency
- TxDOT (Bryan district) · Brazos, Texas
- Letting
- Aug 12, 2026
- Quantity
- 10 LF
- Contractor
- GARRET SHIELDS INFRASTRUCTURE
- Winning price
- $400 / LF
What’s behind $131
A free account opens the full build-up of this number, down to the agency documents it came from.
Middle-half range
The p25–p75 band of winning bids — where most jobs actually land.
Price distribution
All 3 bids charted, so you can see clusters and outliers.
3 observations
Agency, county, letting date, quantity and the price as printed.
3 public bid tabulations
Every row links to the agency’s own document. Check any price yourself.
Email only — no card. Search and medians stay open without an account.
Who let the work, and how agencies and states compare
EstimatorThe median split by developer, city and state DOT, a per-agency comparison where the counts carry it, and the median by state and county for this item.
See what Estimator addsRelated items
Other drainage items priced per LF, ranked by how much evidence each has.
- 42" RC Pipe Culv III$146152 bids
- RC Pipe (CL III)(42 in)$22878 bids
- 42" Reinforced Concrete Pipe Culverts (Class Iii)$12670 bids
- 42" Concrete Pipe Culvert (Class Iii)$21648 bids
- 42" Drainage Pipe$17236 bids
- 42" Side Drain Pipe$63.5032 bids
- Culvert Pipe Reinforced Concrete$1473,171 bids
- 18" Side Drain Pipe$37.00794 bids
3 observations
1 agency in 1 state · lettings Jan 15, 2025 – Aug 12, 2026
| Letting | Agency · County | Quantity | Unit price | Source document |
|---|---|---|---|---|