Conduit, Schedule 40, 3 Inch

Unit LFLettings Jan 9, 2015 – Dec 5, 20251 agency in 1 state

Median winning unit price

Deep 28 winning bids

$12.25/ LF

Winning bids
28
Source documents
27

Winning bids only, as awarded. Nominal dollars. How we compute this

28Winning bids
1Agency
Jan 9, 2015 – Dec 5, 2025Letting period

Where the number comes from

One of the 28 winning bids behind that median, with the agency’s own document one click away.

Agency
MDOT · Michigan
Letting
Dec 5, 2025
Quantity
90 Ft
Contractor
Toebe Construction LLC
Winning price
$10.85 / LF
Open the source pageletting 2025-12-05 · mdotjboss.state.mi.us

Median by quarter

Estimator

How this item has priced over time, quarter by quarter, from the same rows as the headline figure.

See what Estimator adds

What’s behind $12.25

A free account opens the full build-up of this number, down to the agency documents it came from.

  • Middle-half range

    The p25–p75 band of winning bids — where most jobs actually land.

  • Price distribution

    All 28 bids charted, so you can see clusters and outliers.

  • 28 observations

    Agency, county, letting date, quantity and the price as printed.

  • 27 public bid tabulations

    Every row links to the agency’s own document. Check any price yourself.

Email only — no card. Search and medians stay open without an account.

28 observations

1 agency in 1 state · lettings Jan 9, 2015 – Dec 5, 2025

LettingAgency · CountyQuantityUnit priceSource document
28 rows, each with its source document. Sign in to open them.Create free account