37.5 kVA single-phase pole-mount transformer: bid prices

Median bid $2,590 per unit (25th to 75th percentile $1,931 to $3,018) from 43 bids by 2 utilities in 5 documents.

Quoted lead time: median 19 weeks across 22 quotes.

By year

YearMedian25th75thBidsUtilities
2025$2,644$2,264$2,922192

By secondary voltage

SecondaryMedianBids
120/240$2,58022
240/480$2,20215
277/480Y$3,7156

Who bid

BidderBidsMedianUtilities
AR Transformers Inc.4$2,0761
KLLEN Group America4$2,2821
United Utility Supply4$2,0801
American Wire Group (AWG)2$2,9841
Amek ANS Inc.2$2,3821
Anixter/WESCO2$1,7901
Anixter/Wesco/GE2$3,7621
Howard Industries2$4,9061
General Pacific/Ermco2$2,9841
Border States Industries2$1,9621
Border States/First Philec2$4,1701
Resco2$9511

Rows, newest first

Showing 43 of 43. Pro downloads them all as CSV.

OpenedUtilityBidderUnit priceQtyLeadDocument
2026-03-23Geneva Electric, ILAnixter/WESCO$1,7761awardedsource
2026-03-23Geneva Electric, ILKLLEN Group America$1,9201source
2026-03-23Geneva Electric, ILAR Transformers Inc.$1,5631source
2026-03-23Geneva Electric, ILUnited Utility Supply$1,9581awardedsource
2026-03-23Geneva Electric, ILAnixter/WESCO$1,8041awardedsource
2026-03-23Geneva Electric, ILKLLEN Group America$1,9201source
2026-03-23Geneva Electric, ILAR Transformers Inc.$1,4841source
2026-03-23Geneva Electric, ILUnited Utility Supply$1,9391awardedsource
2025-04-07Geneva Electric, ILBorder States Industries$2,002121 wkawardedsource
2025-04-07Geneva Electric, ILTRS Electric SA/United TRS Electric, Inc.$2,8831source
2025-04-07Geneva Electric, ILPulse MAC Solutions LLC$2,875119 wksource
2025-04-07Geneva Electric, ILULS Corporate Inc.$3,5631source
2025-04-07Geneva Electric, ILKLLEN Group America$2,644119 wkawardedsource
2025-04-07Geneva Electric, ILAmerican Wire Group (AWG)$3,007128 wksource
2025-04-07Geneva Electric, ILAR Transformers Inc.$2,590113 wkawardedsource
2025-04-07Geneva Electric, ILUnited Utility Supply$2,204113 wkawardedsource
2025-04-07Geneva Electric, ILAmek ANS Inc.$2,4401source
2025-04-07Geneva Electric, ILBorder States Industries$1,922121 wkawardedsource
2025-04-07Geneva Electric, ILTRS Electric SA/United TRS Electric, Inc.$2,8831source
2025-04-07Geneva Electric, ILPulse MAC Solutions LLC$2,990119 wksource
2025-04-07Geneva Electric, ILULS Corporate Inc.$3,5631source
2025-04-07Geneva Electric, ILKLLEN Group America$2,644119 wkawardedsource
2025-04-07Geneva Electric, ILAmerican Wire Group (AWG)$2,960128 wksource
2025-04-07Geneva Electric, ILAR Transformers Inc.$2,590113 wkawardedsource
2025-04-07Geneva Electric, ILUnited Utility Supply$2,202113 wkawardedsource
2025-04-07Geneva Electric, ILAmek ANS Inc.$2,3231source
2025-03-27Benton PUD, WAAnixter / Cooper/Eaton$1,96910awardedsource
2024-03-21Benton PUD, WAMVA Power Inc.$2,571528 wkawardedsource
2024-03-21Benton PUD, WAGeneral Pacific/Ermco$2,9375source
2024-03-21Benton PUD, WAIrby Utility/Central Moloney$3,480523 wksource
2024-03-21Benton PUD, WAAnixter/Wesco/GE$3,723518 wksource
2024-03-21Benton PUD, WABorder States/First Philec$4,037518 wksource
2024-03-21Benton PUD, WAHoward Industries$4,843560 wksource
2024-03-21Benton PUD, WAMVA Power Inc.$2,5711028 wkawardedsource
2024-03-21Benton PUD, WAGeneral Pacific/Ermco$3,03010source
2024-03-21Benton PUD, WAIrby Utility/Central Moloney$3,6301023 wksource
2024-03-21Benton PUD, WAAnixter/Wesco/GE$3,8001018 wksource
2024-03-21Benton PUD, WABorder States/First Philec$4,3031018 wksource
2024-03-21Benton PUD, WAHoward Industries$4,9681060 wksource
2018-06-11Geneva Electric, ILResco$9721awardedsource
2018-06-11Geneva Electric, ILWesco$9881source
2018-06-11Geneva Electric, ILResco$9301source
2018-06-11Geneva Electric, ILWesco$9201awardedsource

Prices are the unit prices each utility printed for the bidder, as bid. Where a tab prints only a total, the unit price is that total divided by the quantity and labelled. Loss-evaluated (ownership) cost is never shown as a price. Units above 10 MVA are kept apart. A median needs 5 or more bids from 2 or more utilities; below that the page says so instead of showing a number. Every row links to the utility's own document. Not a quote, not an estimate.